Market Notices

124091RESERVE NOTICE04/02/2025 03:01:16 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124059 has been updated at 1420 hrs 04/02/2025 to the following:

[1.] From 1530 hrs 04/02/2025 to 1630 hrs 04/02/2025.
The forecast capacity reserve requirement is 1663 MW.
The minimum capacity reserve available is 1277 MW.

[2.] From 1830 hrs 04/02/2025 to 2030 hrs 04/02/2025.
The forecast capacity reserve requirement is 1652 MW.
The minimum capacity reserve available is 974 MW.


Manager NEM Real Time Operations
     
124084SETTLEMENTS RESIDUE04/02/2025 02:42:10 PM

[EventId:202502041335_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 04 February 2025 13:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1335 hrs on 4 February 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 4 February 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1335 hrs on 4 February 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
124069SETTLEMENTS RESIDUE04/02/2025 01:15:58 PM

[EventId:202502041300_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 04 February 2025 13:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 4 February 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 4 February 2025.

Refer to market notice: 124064

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1300 hrs on 4 February 2025.

This is an AEMO autogenerated Market Notice.
     
124064SETTLEMENTS RESIDUE04/02/2025 11:35:33 AM

[EventId:202502041135_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 04 February 2025 11:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1135 hrs on 4 February 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 4 February 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1135 hrs on 4 February 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
124063GENERAL NOTICE04/02/2025 10:38:35 AM

NEM Local Temperature Alerts for SA, TAS, VIC from 04 Feb 2025 to 08 Feb 2025

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Port Augusta Ap (39+ Deg C): 6th Feb

TAS
Launceston Ti Tree Bend (33+ Deg C): 4th Feb

VIC
Latrobe Valley Ap (39+ Deg C): 4th Feb
Mildura Ap (39+ Deg C): 4th Feb, 6th Feb

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
124059RESERVE NOTICE04/02/2025 04:02:18 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124049 has been updated at 0400 hrs 04/02/2025 to the following:

[1.] From 1630 hrs 04/02/2025 to 2030 hrs 04/02/2025.
The forecast capacity reserve requirement is 1703 MW.
The minimum capacity reserve available is 1136 MW.


Manager NEM Real Time Operations
     
124049RESERVE NOTICE03/02/2025 04:19:18 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1630 hrs 04/02/2025 to 2030 hrs 04/02/2025.
The forecast capacity reserve requirement is 1795 MW.
The minimum capacity reserve available is 1191 MW.


Manager NEM Real Time Operations
     
124044POWER SYSTEM EVENTS03/02/2025 02:13:15 PM

Update - Non-credible contingency event - TAS region - 03/02/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 03/02/2025

Refer AEMO Electricity Market Notice 124043

The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.

Region: TAS

Elements: Farrell - Reece No.1 and No.2 220 kV lines
Duration: 1410 hrs 03/02/2025 until further notice
Constraint set(s) invoked: F-T-FARE_N-2

Manager NEM Real Time Operations
     
124043POWER SYSTEM EVENTS03/02/2025 02:02:24 PM

Non-credible contingency event - TAS region - 03/02/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 03/02/2025

At 1333 hrs the Farrell - Reece No.1 and No.2 220 kV lines tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     