Cancellation - AEMO Intervention Event - SA region 28/03/2025
Cancellation - AEMO Intervention Event - SA region 28/03/2025
Refer to Market Notice 126018
The AEMO Intervention Event and all associated directions are cancelled from 1700 hrs on 01/04/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 126114
Direction is cancelled from: 1630 hrs 01/04/2025
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 126156
Direction is cancelled from: 1700 hrs 01/04/2025
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 126115
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 01/04/2025.
The direction update is issued at 0900 hrs 01/04/2025.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0100 hrs 02/04/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 126064
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 02/04/2025.
The direction update is issued at 1600 hrs 31/03/2025.
Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 126063
The PPCCGT PELICAN POINT direction is now expected to stay in place until 1700 hrs 01/04/2025.
The direction update is issued at 1600 hrs 31/03/2025.
Manager NEM Real Time Operations
CHG0102343 - Frequency Performance Payments (FPP) Maintenance Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Frequency Performance Payments Engine
Change Title: Frequency Performance Payments (FPP) Maintenance Release
Change Start Date & Time: 02/04/2025 09:00:00
Change End Date & Time: 02/04/2025 16:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: During the window, delivery of FPP calculation results may be delayed at various points
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
Completed - CHG0093394 - Planned Outage for the Gas Short Term Trading Market Systems SWEXIE Pre-Production.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: STTM - Market Inputs - Manual
Change Title: Planned Outage for the Gas Short Term Trading Market Systems SWEXIE Pre-Production.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.