Network Augmentation Commissioned - NSW Region - 20/05/2025
Network Augmentation Commissioned - NSW Region - 20/05/2025
At 1700 hrs 20/05/2025, the Buronga No.5 330kV synchronous condenser has been commissioned.
Manager NEM Real Time Operations
Network Augmentation Commissioned - Vic Region - 29/04/2025
Network Augmentation Commissioned - Vic Region - 29/04/2025
At 2030hrs 29/04/2025, the existing Haunted Gully - Tarrone No1 500 kV transmission line has been cut in at Mortlake Power Station to create the following transmission line sections:
Mortlake PS - Tarrone No.1 500 kV transmission line
Mortlake PS - Haunted Gully No.1 500 kV transmission line
Manager NEM Real Time Operations
[EventId:202504271455_review] Prices for interval 27-Apr-2025 14:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 27 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Apr-2025 14:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504271450_review] Prices for interval 27-Apr-2025 14:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1445 hrs on 27 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Apr-2025 14:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504271445_review] Prices for interval 27-Apr-2025 14:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1440 hrs on 27 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Apr-2025 14:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504271440_review] Prices for interval 27-Apr-2025 14:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1435 hrs on 27 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Apr-2025 14:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504271435_review] Prices for interval 27-Apr-2025 14:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 27 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Apr-2025 14:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504271430_review] Prices for interval 27-Apr-2025 14:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1425 hrs on 27 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Apr-2025 14:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504271425_review] Prices for interval 27-Apr-2025 14:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1420 hrs on 27 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Apr-2025 14:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.