PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 02/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1730 hrs 02/06/2025 to 1900 hrs 02/06/2025.
The forecast capacity reserve requirement is 1766 MW.
The minimum capacity reserve available is 1650 MW.
Manager NEM Real Time Operations
Reclassification of non-credible contingency event due to existence of widespread abnormal conditions - All NEM regions.
AEMO has identified that a non-credible contingency event impacting the power system is more likely to occur and is considered reasonably possible because of the existence of widespread abnormal conditions namely Severe Space Weather Watch in all NEM regions.
AEMO has therefore reclassified the occurrence of a non-credible contingency event involving multiple plant due to these abnormal conditions as credible.
Need for further measures is being monitored and further measures may be implemented in line with the Power System Security Guidelines (SO_OP_3715).
Manager NEM Real Time Operations
Cancellation of the Reclassification of a Non-Credible Contingency Event: Loss of the Sheffield - Burnie No. 1 220kV Line, Sheffield - Burnie No. 2 110kV Line and the Ulverstone - Emu Bay 110kV Line in TAS1 due to lightning
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event .
Based on advice received from the asset owner, AEMO no longer considers the trip of the Sheffield - Burnie No. 1 220kV Line, Sheffield - Burnie No. 2 110kV Line and the Ulverstone - Emu Bay 110kV Line in TAS1 due to lightning as a credible contingency when there is lightning activity in the vicinity.
Accordingly the reclassification as a credible contingency is cancelled .
Region: TAS1
Element: Sheffield - Burnie No. 1 220kV Line, Sheffield - Burnie No. 2 110kV Line and the Ulverstone - Emu Bay 110kV Line
Cancellation time: 29/05/2025 1600 hrs
Constraint set(s) revoked: NONE
Refer AEMO Electricity Market Notices 125566
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Armidale Dumaresq 8C and Dumaresq Bulli 8M 330kV lines - NSW region - 28/05/2025
Inter-regional transfer limit variation - Armidale Dumaresq 8C and Dumaresq Bulli 8M 330kV lines - NSW region - 28/05/2025
At 1750 hrs 28/05/2025 there was a short notice outage of Armidale Dumaresq 8C and Dumaresq Bulli 8M 330kV lines.
The following constraint set(s) invoked at 1745 hrs 28/05/2025
N-ARDM_8C
N-X_8C+DM+TW_SVC
and the following constraint set(s) invoked at 1750 hrs 28/05/2025
I-BCDM_ONE
N-X_8L+DM+TW_SVC
These constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
[EventId:202505271740_confirmed] Prices for interval 27-May-2025 17:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 27 May 2025
PRICES ARE NOW CONFIRMED for trading interval 27-May-2025 17:40.
In accordance with Market Notice 127309 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202505271800_confirmed] Prices for interval 27-May-2025 18:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 27 May 2025
PRICES ARE NOW CONFIRMED for trading interval 27-May-2025 18:00.
In accordance with Market Notice 127313 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202505271755_confirmed] Prices for interval 27-May-2025 17:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 27 May 2025
PRICES ARE NOW CONFIRMED for trading interval 27-May-2025 17:55.
In accordance with Market Notice 127312 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202505271750_confirmed] Prices for interval 27-May-2025 17:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 27 May 2025
PRICES ARE NOW CONFIRMED for trading interval 27-May-2025 17:50.
In accordance with Market Notice 127311 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202505271745_confirmed] Prices for interval 27-May-2025 17:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 27 May 2025
PRICES ARE NOW CONFIRMED for trading interval 27-May-2025 17:45.
In accordance with Market Notice 127310 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.