[EventId:202505271640_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 27 May 2025 16:40
Issued by Australian Energy Market Operator Ltd at 1640 hrs on 27 May 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 27 May 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1640 hrs on 27 May 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Cancellation - AEMO Intervention Event - SA region 22/05/2025
Cancellation - AEMO Intervention Event - SA region 22/05/2025
Refer to Market Notice 127159
The AEMO Intervention Event and all associated directions are cancelled from 1400 hrs on 27/05/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127276
Direction is cancelled from: 1400 hrs 27/05/2025
Manager NEM Real Time Operations
Initial - CHG0103591 - Pre-Prod MSATS 54.2 CICD Maintenance Release (MSATS App deployment only)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod MSATS 54.2 CICD Maintenance Release (MSATS App deployment only)
Change Start Date & Time: 28/05/2025 13:00:00
Change End Date & Time: 28/05/2025 17:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Pre-Production
Participant Impact and Requirements: no outage, deployment will be made to msats 1a first then switch to msats 1b.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
[EventId:202505261845_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 26 May 2025 18:45
Issued by Australian Energy Market Operator Ltd at 1845 hrs on 26 May 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 26 May 2025.
Refer to market notice: 127279
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1845 hrs on 26 May 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202505261730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 26 May 2025 17:30
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 26 May 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 26 May 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 26 May 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127232
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 27/05/2025.
The direction update is issued at 1600 hrs 26/05/2025.
Manager NEM Real Time Operations
Completed - CHG0103179 - Scheduled maintenance of Marketnet router in Brisbane
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Local Area Network
Change Title: Scheduled maintenance of Marketnet router in Brisbane
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127193
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 27/05/2025.
The direction update is issued at 1600 hrs 25/05/2025.
Manager NEM Real Time Operations