Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 07/01/2025
In order to maintain the power system in a secure operating state in the VIC region, AEMO has invoked automated constraint set CA_BRIS_5687999A from 0330 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
V-S-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 122861
The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 08/01/2025.
The direction update is issued at 1600 hrs 06/01/2025.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 122860
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 08/01/2025.
The direction update is issued at 1600 hrs 06/01/2025.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/01/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122896 is cancelled at 1430 hrs 06/01/2025.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/01/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122855 has been updated to the following:
[1.] From 1600 hrs 06/01/2025 to 1800 hrs 06/01/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1087 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122863 is cancelled at 2145 hrs 05/01/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1700 hrs 06/01/2025 to 1730 hrs 06/01/2025.
The forecast capacity reserve requirement is 1036 MW.
The minimum capacity reserve available is 982 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 122859
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1500 hrs 05/01/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0200 hrs 06/01/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 07/01/2025.
Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 122859
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1500 hrs 05/01/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0400 hrs 06/01/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 07/01/2025.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations