Market Notices

124162PRICES SUBJECT TO REVIEW05/02/2025 01:06:20 PM

[EventId:202502051310_review] Prices for interval 05-Feb-2025 13:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1305 hrs on 5 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 13:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124161PRICES SUBJECT TO REVIEW05/02/2025 01:10:31 PM

[EventId:202502051305_review] Prices for interval 05-Feb-2025 13:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 5 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 13:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124159PRICES SUBJECT TO REVIEW05/02/2025 01:08:27 PM

[EventId:202502051300_review] Prices for interval 05-Feb-2025 13:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1255 hrs on 5 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 13:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124158PRICES SUBJECT TO REVIEW05/02/2025 12:51:50 PM

[EventId:202502051255_review] Prices for interval 05-Feb-2025 12:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1250 hrs on 5 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 12:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124155PRICES SUBJECT TO REVIEW05/02/2025 12:45:30 PM

[EventId:202502051250_review] Prices for interval 05-Feb-2025 12:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1245 hrs on 5 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 12:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124154RESERVE NOTICE05/02/2025 01:04:37 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124150 has been updated at 1200 hrs 05/02/2025 to the following:

From 1730 hrs to 1830 hrs 07/02/2025.
The forecast capacity reserve requirement is 1063 MW.
The minimum capacity reserve available is 967 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
124150RESERVE NOTICE05/02/2025 11:04:33 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124143 has been updated at 1000 hrs 05/02/2025 to the following:

From 1630 hrs to 1900 hrs 07/02/2025.
The forecast capacity reserve requirement is 1161 MW.
The minimum capacity reserve available is 883 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
124149RESERVE NOTICE05/02/2025 10:58:02 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 11/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 124147 is cancelled at 1000 hrs 05/02/2025.

No LOR2 condition is currently forecast in the SA region in the STPASA period.

AEMO Operations
     
124147RESERVE NOTICE05/02/2025 09:51:53 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 11/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 1800 hrs to 2030 hrs 11/02/2025.
The forecast capacity reserve requirement is 222 MW.
The minimum capacity reserve available is 180 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm