Market Notices

125978RECLASSIFY CONTINGENCY26/03/2025 05:39:16 PM

Cancellation of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV

Cancellation time: 26/03/2025 17:39

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 125957

Auto-generated on behalf of Manager NEM Real Time Operations
     
125977RECLASSIFY CONTINGENCY26/03/2025 05:39:15 PM

Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Cancellation time: 26/03/2025 17:39

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 125956

Auto-generated on behalf of Manager NEM Real Time Operations
     
125970PRICES SUBJECT TO REVIEW26/03/2025 04:55:12 PM

[EventId:202503261700_review] Prices for interval 26-Mar-2025 17:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1655 hrs on 26 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 26-Mar-2025 17:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125969PRICES SUBJECT TO REVIEW26/03/2025 04:50:13 PM

[EventId:202503261655_review] Prices for interval 26-Mar-2025 16:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1650 hrs on 26 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 26-Mar-2025 16:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125968PRICES SUBJECT TO REVIEW26/03/2025 04:45:18 PM

[EventId:202503261650_review] Prices for interval 26-Mar-2025 16:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1645 hrs on 26 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 26-Mar-2025 16:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125967PRICES SUBJECT TO REVIEW26/03/2025 04:40:16 PM

[EventId:202503261645_review] Prices for interval 26-Mar-2025 16:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1640 hrs on 26 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 26-Mar-2025 16:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125966PRICES SUBJECT TO REVIEW26/03/2025 04:35:14 PM

[EventId:202503261640_review] Prices for interval 26-Mar-2025 16:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1635 hrs on 26 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 26-Mar-2025 16:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125965PRICES SUBJECT TO REVIEW26/03/2025 04:30:24 PM

[EventId:202503261635_review] Prices for interval 26-Mar-2025 16:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1630 hrs on 26 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 26-Mar-2025 16:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125963POWER SYSTEM EVENTS26/03/2025 04:20:27 PM

Non-credible contingency event - TAS region - 26/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 26/03/2025

At 1551 hrs the Palmerston A 220kV Bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

Approximately 40MW of generation was disconnected.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.


Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm