Filter by category
Filter by Date
NON-CONFORMANCE Region QLD1 Wednesday, 19 February 2025
NON-CONFORMANCE QLD1 Region Wednesday, 19 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 19/02/2025 11:55 to 19/02/2025 12:10
Amount: -18 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202502191125_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 19 February 2025 11:25
Issued by Australian Energy Market Operator Ltd at 1125 hrs on 19 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 19 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1125 hrs on 19 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502190940_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 19 February 2025 09:40
Issued by Australian Energy Market Operator Ltd at 0940 hrs on 19 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 19 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0940 hrs on 19 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502190930_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 19 February 2025 09:30
Issued by Australian Energy Market Operator Ltd at 0930 hrs on 19 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 19 February 2025.
Refer to market notice: 124856
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 0930 hrs on 19 February 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202502190835_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 19 February 2025 08:35
Issued by Australian Energy Market Operator Ltd at 0835 hrs on 19 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 19 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0835 hrs on 19 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502181825_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 18 February 2025 18:25
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 18 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 18 February 2025.
Refer to market notice: 124852
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1825 hrs on 18 February 2025.
This is an AEMO autogenerated Market Notice.
Cancellation of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV
Cancellation time: 18/02/2025 17:33
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 124851
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV
Cancellation time: 18/02/2025 17:33
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 124850
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202502181705_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 18 February 2025 17:05
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 18 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 18 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1705 hrs on 18 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.