Filter by category
Filter by Date
Update to Victorian system normal Kerang voltage stability limit
AEMO has completed a review of a system normal voltage stability limit in north west Victoria as a result of commissioning of BESS at Koorangie. The revised limit manages pre-contingent flow on the Wemen to Koorangie 220 kV line to avoid voltage collapse at Koorangie, Kerang or Wemen on loss of the Crowlands to Bulgana to Horsham or Horsham to Murra Warra to Kiamal 220 kV line. The revised constraint equation includes the generators in south-west NSW and north-west Victoria on the left-hand side as well as Murraylink and V-SA. Full details on the limits advice are to be published shortly on the AEMO website: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice
The revised limit will be implemented at 0900 hrs on Monday 31st March 2025, by updating V^^V_NIL_KGTS.
For full details on the factors this constraint equation has now been loaded into AEMO's pre-production systems.
For further details on this constraint equation please contact terry.liu@aemo.com.au
Terry Liu
AEMO Operations
[EventId:202503261700_review] Prices for interval 26-Mar-2025 17:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1655 hrs on 26 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 26-Mar-2025 17:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503261655_review] Prices for interval 26-Mar-2025 16:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1650 hrs on 26 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 26-Mar-2025 16:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503261650_review] Prices for interval 26-Mar-2025 16:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 26 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 26-Mar-2025 16:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503261645_review] Prices for interval 26-Mar-2025 16:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1640 hrs on 26 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 26-Mar-2025 16:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503261640_review] Prices for interval 26-Mar-2025 16:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1635 hrs on 26 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 26-Mar-2025 16:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503261635_review] Prices for interval 26-Mar-2025 16:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 26 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 26-Mar-2025 16:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Non-credible contingency event - TAS region - 26/03/2025
Non-credible contingency event - TAS region - 26/03/2025
At 1551 hrs the Palmerston A 220kV Bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
Approximately 40MW of generation was disconnected.
The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 25 March 2025
NON-CONFORMANCE QLD1 Region Tuesday, 25 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 25/03/2025 14:55 to 25/03/2025 15:45
Amount: -55 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations