Filter by category
Filter by Date
Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV
Duration: 13/02/2025 18:28 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV
Duration: 13/02/2025 18:28 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 13/02/2025
Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 13/02/2025
At 1738 hrs 13/02/2025 there was an unplanned outage of the Greenbank 275kV SVC.
The following constraint set(s) invoked at 1745 hrs 13/02/2025
Q-GB_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Directlink- NSW region - 13/02/2025
Inter-regional transfer limit variation - No.2 Leg of Directlink - NSW region - 13/02/2025
A planned outage of the No.2 Leg of Directlink in the NSW region was scheduled from 1517 hrs 30/01/2025 to 1700 hrs 20/02/2025.
The outage has been completed and the No.2 Leg of Directlink returned to service at 1312 hrs 13/02/2025
Constraint set(s) revoked: N-X_MBTE_2
Manager NEM Real Time Operations
[EventId:202502131150_confirmed] Prices for interval 13-Feb-2025 11:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1215 hrs on 13 February 2025
PRICES ARE NOW CONFIRMED for trading interval 13-Feb-2025 11:50.
In accordance with Market Notice 124599 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502131215_confirmed] Prices for interval 13-Feb-2025 12:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1215 hrs on 13 February 2025
PRICES ARE NOW CONFIRMED for trading interval 13-Feb-2025 12:15.
In accordance with Market Notice 124604 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502131210_confirmed] Prices for interval 13-Feb-2025 12:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1215 hrs on 13 February 2025
PRICES ARE NOW CONFIRMED for trading interval 13-Feb-2025 12:10.
In accordance with Market Notice 124603 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502131205_confirmed] Prices for interval 13-Feb-2025 12:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1215 hrs on 13 February 2025
PRICES ARE NOW CONFIRMED for trading interval 13-Feb-2025 12:05.
In accordance with Market Notice 124602 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502131200_confirmed] Prices for interval 13-Feb-2025 12:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1215 hrs on 13 February 2025
PRICES ARE NOW CONFIRMED for trading interval 13-Feb-2025 12:00.
In accordance with Market Notice 124601 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.