Reclassification of a Non-Credible Contingency Event: Yallourn - Rowville 7 220 kV line and Yallourn - Rowville 8 220 kV line in VIC1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: VIC1
Lines: Yallourn - Rowville 7 220 kV and Yallourn - Rowville 8 220 kV
Duration: 13/02/2025 19:33 until further notice
Constraint set(s) invoked:
V-ROYP78_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Tungatinah-Lake Echo-Waddamana 1 110kV line and Tungatinah-Waddamana 2 110kV line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Tungatinah-Lake Echo-Waddamana 1 110kV and Tungatinah-Waddamana 2 110kV
Duration: 13/02/2025 19:16 until further notice
Constraint set(s) invoked:
T-TUWA12_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202502131815_confirmed] Prices for interval 13-Feb-2025 18:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1840 hrs on 13 February 2025
PRICES ARE NOW CONFIRMED for trading interval 13-Feb-2025 18:15.
In accordance with Market Notice 124623 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502131840_confirmed] Prices for interval 13-Feb-2025 18:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1840 hrs on 13 February 2025
PRICES ARE NOW CONFIRMED for trading interval 13-Feb-2025 18:40.
In accordance with Market Notice 124630 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502131835_confirmed] Prices for interval 13-Feb-2025 18:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1840 hrs on 13 February 2025
PRICES ARE NOW CONFIRMED for trading interval 13-Feb-2025 18:35.
In accordance with Market Notice 124629 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502131830_confirmed] Prices for interval 13-Feb-2025 18:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1840 hrs on 13 February 2025
PRICES ARE NOW CONFIRMED for trading interval 13-Feb-2025 18:30.
In accordance with Market Notice 124626 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502131825_confirmed] Prices for interval 13-Feb-2025 18:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1840 hrs on 13 February 2025
PRICES ARE NOW CONFIRMED for trading interval 13-Feb-2025 18:25.
In accordance with Market Notice 124625 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502131820_confirmed] Prices for interval 13-Feb-2025 18:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1840 hrs on 13 February 2025
PRICES ARE NOW CONFIRMED for trading interval 13-Feb-2025 18:20.
In accordance with Market Notice 124624 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV
Duration: 13/02/2025 18:28 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations