Filter by category
Filter by Date
Cancellation of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line
Cancellation time: 15/03/2025 17:33
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 125672
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202503151620_confirmed] Prices for interval 15-Mar-2025 16:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 15 March 2025
PRICES ARE NOW CONFIRMED for trading interval 15-Mar-2025 16:20.
In accordance with Market Notice 125673 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503151645_confirmed] Prices for interval 15-Mar-2025 16:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 15 March 2025
PRICES ARE NOW CONFIRMED for trading interval 15-Mar-2025 16:45.
In accordance with Market Notice 125681 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503151640_confirmed] Prices for interval 15-Mar-2025 16:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 15 March 2025
PRICES ARE NOW CONFIRMED for trading interval 15-Mar-2025 16:40.
In accordance with Market Notice 125679 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503151635_confirmed] Prices for interval 15-Mar-2025 16:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 15 March 2025
PRICES ARE NOW CONFIRMED for trading interval 15-Mar-2025 16:35.
In accordance with Market Notice 125677 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503151630_confirmed] Prices for interval 15-Mar-2025 16:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 15 March 2025
PRICES ARE NOW CONFIRMED for trading interval 15-Mar-2025 16:30.
In accordance with Market Notice 125676 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503151625_confirmed] Prices for interval 15-Mar-2025 16:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 15 March 2025
PRICES ARE NOW CONFIRMED for trading interval 15-Mar-2025 16:25.
In accordance with Market Notice 125674 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Reclassification of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line
Duration: 15/03/2025 15:52 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Direction - SA region 15/03/2025
Direction - SA region 15/03/2025
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1600 hrs on 15/03/2025.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations