[EventId:202502140905_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 14 February 2025 09:05
Issued by Australian Energy Market Operator Ltd at 0905 hrs on 14 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 14 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0905 hrs on 14 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502131840_review] Prices for interval 13-Feb-2025 18:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1835 hrs on 13 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Feb-2025 18:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502131835_review] Prices for interval 13-Feb-2025 18:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 13 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Feb-2025 18:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502131830_review] Prices for interval 13-Feb-2025 18:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 13 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Feb-2025 18:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502131825_review] Prices for interval 13-Feb-2025 18:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 13 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Feb-2025 18:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502131820_review] Prices for interval 13-Feb-2025 18:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 13 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Feb-2025 18:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502131815_review] Prices for interval 13-Feb-2025 18:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1810 hrs on 13 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Feb-2025 18:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Cancellation of Forecast Minimum System Load (MSL) MSL1 event in the Vic Region on 16/02/2025
Cancellation - Forecast MSL1 - VIC Region at 1400 hrs 13/02/2025.
Refer to Market Notice 124560 for MSL1.
AEMO Operations
[EventId:202502131215_review] Prices for interval 13-Feb-2025 12:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1210 hrs on 13 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Feb-2025 12:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.