[EventId:202501291105_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 29 January 2025 11:05
Issued by Australian Energy Market Operator Ltd at 1105 hrs on 29 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 29 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1105 hrs on 29 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202501291100_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 January 2025 11:00
Issued by Australian Energy Market Operator Ltd at 1100 hrs on 29 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 January 2025.
Refer to market notice: 123857
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1100 hrs on 29 January 2025.
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - TIPS - Para 275kV Line- SA region - 29/01/2025
Inter-regional transfer limit variation - TIPS - Para 275kV Line - SA region - 29/01/2025
At 0930 hrs 29/01/2025 there was a short notice outage of TIPS - Para 275kV Line.
The following constraint set(s) invoked at 0930 hrs 29/01/2025
S-X_MGTI+PATI
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
[EventId:202501290930_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 January 2025 09:30
Issued by Australian Energy Market Operator Ltd at 0930 hrs on 29 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0930 hrs on 29 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202501281845_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 28 January 2025 18:45
Issued by Australian Energy Market Operator Ltd at 1845 hrs on 28 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 28 January 2025.
Refer to market notice: 123810
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1845 hrs on 28 January 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202501281800_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 28 January 2025 18:00
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 28 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 28 January 2025.
Refer to market notice: 123814
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1800 hrs on 28 January 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202501281535_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 28 January 2025 15:35
Issued by Australian Energy Market Operator Ltd at 1535 hrs on 28 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 28 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1535 hrs on 28 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 123761
TORRB2 TORRENS ISLAN at 0030 hrs 27/01/2025 to Remain synchronised and follow dispatch targets.
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 30/01/2025.
The direction update is issued at 1410 hrs 28/01/2025.
Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 123762
PPCCGT PELICAN POINT at 0100 hrs 27/01/2025 to Remain synchronised and follow dispatch targets.
The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 30/01/2025.
The direction update is issued at 1410 hrs 28/01/2025.
Manager NEM Real Time Operations