CHG0101145 | Production | Planned Maintenance to Norwest Internet Router
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Internet Access
Change Title: Planned Maintenance to Norwest Internet Router
Change Start Date & Time: 15/02/2025 10:00:00 AEST
Change End Date & Time: 15/02/2025 15:00:00 AEST
Outage Start Date & Time: 15/02/2025 11:00:00 AEST
Outage End Date & Time: 15/02/2025 13:00:00 AEST
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:
IPWAN Participants - Nil
Lan-2-Lan VPN Participants (IPSEC) - Up to 1 Hour outage for participants who have established their VPN connection/s via the AEMO NSW datacenter termination point (202.44.78.10 for Policy Based VPN and 202.44.78.12 for Route Based VPN) only - All L2L connections should be established to both QLD / NSW.
B2B VPN - Up to 1 hour outage to TNSPs with B2B VPN to AEMO NSW Datacentre if VPN connection is only terminating in NSW only.
SSL VPN Participants: None expected as DNS entry will be updated to remove NSW IP.
GASHUB: Nil
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO QLD datacenter termination point 202.44.76.10 for Policy Based VPN and 202.44.76.12 for Route Based VPN) prior to this scheduled outage.
*** Failure to do so will impact connectivity to Marketnet Services. ***
Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 124254
PPCCGT PELICAN POINT at 0730 hrs 07/02/2025 to Remain synchronised and follow dispatch targets.
The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 09/02/2025.
The direction update is issued at 1410 hrs 07/02/2025.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 124255
TORRB2 TORRENS ISLAN at 0730 hrs 07/02/2025 to Remain synchronised and follow dispatch targets.
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 09/02/2025.
The direction update is issued at 1410 hrs 07/02/2025.
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 124253
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1500 hrs 06/02/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0730 hrs 07/02/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 08/02/2025 / further notice.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 124253
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1510 hrs 06/02/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0730 hrs 07/02/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 08/02/2025 / further notice.
Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region 06/02/2025
Direction - SA region 06/02/2025
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1505 hrs on 06/02/2025.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 124240
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0730 hrs 06/02/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1500 hrs 06/02/2025, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 06/02/2025
Cancellation - AEMO Intervention Event - SA region 06/02/2025
Refer to Market Notice 124204
The AEMO Intervention Event and all associated directions are cancelled from 1300 hrs on 06/02/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 124182
Direction is cancelled from: 1300 hrs 06/02/2025
Manager NEM Real Time Operations