125074SETTLEMENTS RESIDUE24/02/2025 03:30:23 PM

[EventId:202502241530_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 24 February 2025 15:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1530 hrs on 24 February 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 February 2025.

Refer to market notice: 125071

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1530 hrs on 24 February 2025.

This is an AEMO autogenerated Market Notice.
     
125071SETTLEMENTS RESIDUE24/02/2025 02:35:33 PM

[EventId:202502241435_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 24 February 2025 14:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1435 hrs on 24 February 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 February 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1435 hrs on 24 February 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
125069SETTLEMENTS RESIDUE24/02/2025 01:00:32 PM

[EventId:202502241300_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 24 February 2025 13:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 24 February 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 February 2025.

Refer to market notice: 125068

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1300 hrs on 24 February 2025.

This is an AEMO autogenerated Market Notice.
     
125068SETTLEMENTS RESIDUE24/02/2025 11:05:27 AM

[EventId:202502241105_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 24 February 2025 11:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1105 hrs on 24 February 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 February 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1105 hrs on 24 February 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
125052PRICES SUBJECT TO REVIEW23/02/2025 03:05:22 PM

[EventId:202502231510_review] Prices for interval 23-Feb-2025 15:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1505 hrs on 23 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 23-Feb-2025 15:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125050PRICES SUBJECT TO REVIEW23/02/2025 03:00:24 PM

[EventId:202502231505_review] Prices for interval 23-Feb-2025 15:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1500 hrs on 23 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 23-Feb-2025 15:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125049PRICES SUBJECT TO REVIEW23/02/2025 02:55:17 PM

[EventId:202502231500_review] Prices for interval 23-Feb-2025 15:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1455 hrs on 23 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 23-Feb-2025 15:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125048PRICES SUBJECT TO REVIEW23/02/2025 02:50:21 PM

[EventId:202502231455_review] Prices for interval 23-Feb-2025 14:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1450 hrs on 23 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 23-Feb-2025 14:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125047PRICES SUBJECT TO REVIEW23/02/2025 02:45:25 PM

[EventId:202502231450_review] Prices for interval 23-Feb-2025 14:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1445 hrs on 23 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 23-Feb-2025 14:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm