Market Notices

124359RECLASSIFY CONTINGENCY08/02/2025 02:13:30 PM

Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 08/02/2025 14:13 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
124356RECLASSIFY CONTINGENCY08/02/2025 02:03:55 PM

Reclassification of a Non-Credible Contingency Event: Kamerunga - Barron Gorge 7184 132kV line and Kamerunga - Barron Gorge 7143 132kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Kamerunga - Barron Gorge 7184 132kV and Kamerunga - Barron Gorge 7143 132kV

Duration: 08/02/2025 14:03 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
124343RECLASSIFY CONTINGENCY08/02/2025 12:32:11 PM

Reclassification of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Duration: 08/02/2025 12:32 until further notice

Constraint set(s) invoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Auto-generated on behalf of Manager NEM Real Time Operations
     
124342RECLASSIFY CONTINGENCY08/02/2025 12:32:11 PM

Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Duration: 08/02/2025 12:32 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
124341RECLASSIFY CONTINGENCY08/02/2025 11:34:45 AM

Cancellation of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Cancellation time: 08/02/2025 11:34

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 124340

Auto-generated on behalf of Manager NEM Real Time Operations
     
124340RECLASSIFY CONTINGENCY08/02/2025 09:33:25 AM

Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Duration: 08/02/2025 09:33 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
124324RECLASSIFY CONTINGENCY08/02/2025 06:24:45 AM

Cancellation of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV

Cancellation time: 08/02/2025 06:24

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 124323

Auto-generated on behalf of Manager NEM Real Time Operations
     
124323RECLASSIFY CONTINGENCY08/02/2025 05:21:25 AM

Reclassification of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV

Duration: 08/02/2025 05:21 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
124322RESERVE NOTICE07/02/2025 07:40:53 PM

Cancellation of Actual (LOR1) condition in the NSW region - 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 07/02/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124305 is cancelled at 1940 hrs 07/02/2025.