Market Notices

122460RECLASSIFY CONTINGENCY24/12/2024 05:19:05 PM

Reclassification of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV

Duration: 24/12/2024 17:19 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
122458RECLASSIFY CONTINGENCY24/12/2024 03:58:21 PM

Reclassification of a Non-Credible Contingency Event: Guybal Munjan - Chalumbin 857 275kV line line and Guybal Munjan - Chalumbin 858 275kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Guybal Munjan - Chalumbin 857 275kV line and Guybal Munjan - Chalumbin 858 275kV line

Duration: 24/12/2024 15:58 until further notice

Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
122457RECLASSIFY CONTINGENCY24/12/2024 02:43:07 PM

Reclassification of a Non-Credible Contingency Event: Kamerunga - Barron Gorge No.7184 and Kamerunga - Barron Gorge No.7143 132kV lines in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Kamerunga - Barron Gorge No.7184 and Kamerunga - Barron Gorge No.7143 132kV lines

Duration: 24/12/2024 14:31 until further notice

Constraint set(s) invoked:
NONE

Manager NEM Real Time Operations
     
122456RECLASSIFY CONTINGENCY24/12/2024 02:29:45 PM

Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 24/12/2024 14:29 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
122455RECLASSIFY CONTINGENCY24/12/2024 02:29:45 PM

Reclassification of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 24/12/2024 14:29 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
122454MINIMUM SYSTEM LOAD24/12/2024 02:49:15 PM

Cancellation of Forecast Minimum System Load MSL1 event in the VIC Region on 29/12/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Forecast MSL1 - VIC Region at 1400 hrs 24/12/2024.

Refer to Market Notice 122437 for MSL1.

AEMO Operations
     
122437MINIMUM SYSTEM LOAD23/12/2024 02:38:20 PM

Forecast Minimum System Load (MSL1) condition in the VIC region on 29/12/2024

AEMO ELECTRICITY MARKET NOTICE
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 29/12/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1760 MW
o MSL2 - 1260 MW
o MSL3 - 760 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:

From 1000 hrs 29/12/2024 to 1400 hrs 29/12/2024. Minimum regional demand is forecast to be 1515 MW at 1230 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

AEMO Operations
     
122434RECLASSIFY CONTINGENCY23/12/2024 05:39:21 AM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 23/12/2024 05:39

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 122428

Auto-generated on behalf of Manager NEM Real Time Operations
     
122433RECLASSIFY CONTINGENCY23/12/2024 04:22:36 AM

Cancellation of a Non-Credible Contingency Event: Kamerunga to Barron Gorge No.7184 132 kV and the Kamerunga to Barron Gorge No.7143 132 kV lines in QLD due to lightning.

AEMO ELECTRICITY MARKET NOTICE.

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD

Lines: Kamerunga to Barron Gorge No.7184 132 kV and the Kamerunga to Barron Gorge No.7143 132 kV lines

Cancellation time: 23/12/2024 04:20

Constraint set(s) invoked: Nil

Refer AEMO Electricity Market Notice 122409

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm