Filter by category
Filter by Date
Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: VIC1
Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV
Duration: 22/02/2025 16:45 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202502221635_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 22 February 2025 16:35
Issued by Australian Energy Market Operator Ltd at 1635 hrs on 22 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 22 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.
The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1635 hrs on 22 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Reclassification of a Non-Credible Contingency Event: Strathmore - Clare South No.7208 132 kV line and Strathmore - Clare South tee King Creek No.7128 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Strathmore - Clare South No.7208 132 kV and Strathmore - Clare South tee King Creek No.7128 132 kV
Duration: 22/02/2025 16:00 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202502221505_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 22 February 2025 15:05
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 22 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 22 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1505 hrs on 22 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502211205_confirmed] Prices for interval 21-Feb-2025 12:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 21 February 2025
PRICES ARE NOW CONFIRMED for trading interval 21-Feb-2025 12:05.
In accordance with Market Notice 124967 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502211230_confirmed] Prices for interval 21-Feb-2025 12:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 21 February 2025
PRICES ARE NOW CONFIRMED for trading interval 21-Feb-2025 12:30.
In accordance with Market Notice 124974 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502211225_confirmed] Prices for interval 21-Feb-2025 12:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 21 February 2025
PRICES ARE NOW CONFIRMED for trading interval 21-Feb-2025 12:25.
In accordance with Market Notice 124973 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502211220_confirmed] Prices for interval 21-Feb-2025 12:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 21 February 2025
PRICES ARE NOW CONFIRMED for trading interval 21-Feb-2025 12:20.
In accordance with Market Notice 124972 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502211215_confirmed] Prices for interval 21-Feb-2025 12:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 21 February 2025
PRICES ARE NOW CONFIRMED for trading interval 21-Feb-2025 12:15.
In accordance with Market Notice 124970 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.