123966MARKET INTERVENTION01/02/2025 03:57:13 AM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 123925

Direction is cancelled from: 0400 hrs 01/02/2025

Manager NEM Real Time Operations
     
123965MARKET INTERVENTION31/01/2025 03:59:12 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123924

PPCCGT PELICAN POINT at 0100 hrs 27/01/2025 to Remain synchronised and follow dispatch targets.

The PPCCGT PELICAN POINT direction is now expected to stay in place until 1600 hrs 01/02/2025.

The direction update is issued at 1600 hrs 31/01/2025.

Manager NEM Real Time Operations
     
123957NON-CONFORMANCE31/01/2025 11:31:33 AM

NON-CONFORMANCE Region NSW1 Friday, 31 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 31 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 31/01/2025 11:05 to 31/01/2025 11:30
Amount: -226 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123956GENERAL NOTICE31/01/2025 11:25:03 AM

Project Energy Connect (PEC-1) testing 31th January 2025 1100-1500 for flows from South Australia to Victoria direction up to 150 MW

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 123676

There is an opportunity for testing Project Energy Connect (PEC-1) for flows from South Australia to Victoria direction up to 150 MW on 31th January from 11:00hrs to 15:00hrs

This test includes switching of transmission lines and reactive plant in South Australia and in New South Wales.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

AEMO Operations
     
123955GENERAL NOTICE31/01/2025 10:23:28 AM

NEM Local Temperature Alerts for SA, TAS, VIC from 31 Jan 2025 to 04 Feb 2025

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Adelaide West Terrace (39+ Deg C): 3rd Feb
Clare High School (39+ Deg C): 2nd Feb, 3rd Feb, 4th Feb
Mt Gambier Ap (39+ Deg C): 2nd Feb, 3rd Feb
Port Augusta Ap (39+ Deg C): 1st Feb, 2nd Feb, 3rd Feb, 4th Feb

TAS
Launceston Ti Tree Bend (33+ Deg C): 2nd Feb, 3rd Feb, 4th Feb

VIC
Latrobe Valley Ap (39+ Deg C): 2nd Feb
Mildura Ap (39+ Deg C): 1st Feb, 2nd Feb, 3rd Feb, 4th Feb
Mortlake (39+ Deg C): 3rd Feb

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
123943PRICES SUBJECT TO REVIEW30/01/2025 06:42:26 PM

[EventId:202501301835_review] Prices for interval 30-Jan-2025 18:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 30 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 30-Jan-2025 18:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
123942PRICES SUBJECT TO REVIEW30/01/2025 06:29:45 PM

[EventId:202501301830_review] Prices for interval 30-Jan-2025 18:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1825 hrs on 30 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 30-Jan-2025 18:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
123941PRICES SUBJECT TO REVIEW30/01/2025 06:23:31 PM

[EventId:202501301825_review] Prices for interval 30-Jan-2025 18:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1820 hrs on 30 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 30-Jan-2025 18:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
123940PRICES SUBJECT TO REVIEW30/01/2025 06:17:20 PM

[EventId:202501301820_review] Prices for interval 30-Jan-2025 18:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1815 hrs on 30 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 30-Jan-2025 18:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs