123980INTER-REGIONAL TRANSFER01/02/2025 08:53:03 AM

Inter-regional transfer limit variation - Armidale - Tamworth No. 86 330 kV Line - NSW region - 01/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale - Tamworth No. 86 330 kV Line - NSW region - 01/02/2025

A planned outage of Armidale - Tamworth No. 86 330 kV Line in the NSW region was scheduled to be completed at 1030 hrs 01/02/2025

The outage has been completed by 0835 hrs 01/02/2025

Constraint set(s) invoked:
N-ARTW_86
N-DM_SVC
N-TW_SVC


This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
T-V-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
123957NON-CONFORMANCE31/01/2025 11:31:33 AM

NON-CONFORMANCE Region NSW1 Friday, 31 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 31 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 31/01/2025 11:05 to 31/01/2025 11:30
Amount: -226 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123956GENERAL NOTICE31/01/2025 11:25:03 AM

Project Energy Connect (PEC-1) testing 31th January 2025 1100-1500 for flows from South Australia to Victoria direction up to 150 MW

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 123676

There is an opportunity for testing Project Energy Connect (PEC-1) for flows from South Australia to Victoria direction up to 150 MW on 31th January from 11:00hrs to 15:00hrs

This test includes switching of transmission lines and reactive plant in South Australia and in New South Wales.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

AEMO Operations
     
123955GENERAL NOTICE31/01/2025 10:23:28 AM

NEM Local Temperature Alerts for SA, TAS, VIC from 31 Jan 2025 to 04 Feb 2025

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Adelaide West Terrace (39+ Deg C): 3rd Feb
Clare High School (39+ Deg C): 2nd Feb, 3rd Feb, 4th Feb
Mt Gambier Ap (39+ Deg C): 2nd Feb, 3rd Feb
Port Augusta Ap (39+ Deg C): 1st Feb, 2nd Feb, 3rd Feb, 4th Feb

TAS
Launceston Ti Tree Bend (33+ Deg C): 2nd Feb, 3rd Feb, 4th Feb

VIC
Latrobe Valley Ap (39+ Deg C): 2nd Feb
Mildura Ap (39+ Deg C): 1st Feb, 2nd Feb, 3rd Feb, 4th Feb
Mortlake (39+ Deg C): 3rd Feb

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
123949PRICES UNCHANGED30/01/2025 07:12:37 PM

[EventId:202501301815_confirmed] Prices for interval 30-Jan-2025 18:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 30 January 2025

PRICES ARE NOW CONFIRMED for trading interval 30-Jan-2025 18:15.

In accordance with Market Notice 123939 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
123948PRICES UNCHANGED30/01/2025 07:06:46 PM

[EventId:202501301835_confirmed] Prices for interval 30-Jan-2025 18:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 30 January 2025

PRICES ARE NOW CONFIRMED for trading interval 30-Jan-2025 18:35.

In accordance with Market Notice 123943 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
123947PRICES UNCHANGED30/01/2025 07:00:52 PM

[EventId:202501301830_confirmed] Prices for interval 30-Jan-2025 18:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 30 January 2025

PRICES ARE NOW CONFIRMED for trading interval 30-Jan-2025 18:30.

In accordance with Market Notice 123942 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
123946PRICES UNCHANGED30/01/2025 06:54:38 PM

[EventId:202501301825_confirmed] Prices for interval 30-Jan-2025 18:25 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 30 January 2025

PRICES ARE NOW CONFIRMED for trading interval 30-Jan-2025 18:25.

In accordance with Market Notice 123941 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
123945PRICES UNCHANGED30/01/2025 06:48:32 PM

[EventId:202501301820_confirmed] Prices for interval 30-Jan-2025 18:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 30 January 2025

PRICES ARE NOW CONFIRMED for trading interval 30-Jan-2025 18:20.

In accordance with Market Notice 123940 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.