Market Notices

125090MARKET INTERVENTION25/02/2025 03:56:59 PM

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 125089


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 25/02/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0800 hrs 26/02/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1500 hrs 26/02/2025 / further notice.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
125089MARKET INTERVENTION25/02/2025 03:57:10 PM

Direction - SA region 25/02/2025

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 25/02/2025

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 25/02/2025.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
125088MARKET INTERVENTION25/02/2025 03:29:13 PM

Cancellation - AEMO Intervention Event - SA region 22/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 22/02/2025

Refer to Market Notice 124994

The AEMO Intervention Event and all associated directions are cancelled from 1530 hrs on 25/02/2025.


Manager NEM Real Time Operations
     
125087MARKET INTERVENTION25/02/2025 03:27:57 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 125073

Direction is cancelled from: 1530 hrs 25/02/2025

Manager NEM Real Time Operations
     
125086MARKET INTERVENTION25/02/2025 02:57:13 PM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 125072

Direction is cancelled from: 1500 hrs 25/02/2025

Manager NEM Real Time Operations
     
125085MARKET INTERVENTION25/02/2025 02:18:49 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 125084

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 26/02/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 25/02/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
125084MARKET INTERVENTION25/02/2025 01:01:24 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 26/02/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
125081CONSTRAINTS25/02/2025 08:31:51 AM

Yass to Wagga control scheme change - removal system normal constraint equations in NSW managing 990, 991 and 970 132kV lines

AEMO ELECTRICITY MARKET NOTICE

Transgrid has advised AEMO of an update to the Yass overload trip scheme. The scheme is normally armed managing line flow on 990, 991, 970 132kV lines and it is now operating both directions of flow from Wagga to Yass.

Based on this advice, the following constraint equations will be removed from the NSW system normal constraint sets N-NIL and N-NIL_991, effective immediately.

N>>NIL_970_051
N>>NIL_990_051
N>>NIL_991_051

Ben Blake
AEMO Operations
     
125073MARKET INTERVENTION24/02/2025 03:57:33 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 125053

TORRB2 TORRENS ISLAN at 0030 hrs 23/02/2025 to Remain synchronised and follow dispatch targets.

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1530 hrs 25/02/2025.

The direction update is issued at 1600 hrs 24/02/2025.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm