126803SETTLEMENTS RESIDUE30/04/2025 01:05:26 PM

[EventId:202504301305_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 30 April 2025 13:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1305 hrs on 30 April 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 April 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1305 hrs on 30 April 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
126802MARKET INTERVENTION30/04/2025 01:00:15 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0830 hrs 01/05/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
126794PRICES SUBJECT TO REVIEW30/04/2025 11:00:18 AM

[EventId:202504301105_review] Prices for interval 30-Apr-2025 11:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1100 hrs on 30 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 30-Apr-2025 11:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126793PRICES SUBJECT TO REVIEW30/04/2025 10:55:21 AM

[EventId:202504301100_review] Prices for interval 30-Apr-2025 11:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1055 hrs on 30 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 30-Apr-2025 11:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126792PRICES SUBJECT TO REVIEW30/04/2025 10:50:16 AM

[EventId:202504301055_review] Prices for interval 30-Apr-2025 10:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1050 hrs on 30 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 30-Apr-2025 10:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126791PRICES SUBJECT TO REVIEW30/04/2025 10:45:26 AM

[EventId:202504301050_review] Prices for interval 30-Apr-2025 10:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1045 hrs on 30 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 30-Apr-2025 10:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126790PRICES SUBJECT TO REVIEW30/04/2025 10:40:19 AM

[EventId:202504301045_review] Prices for interval 30-Apr-2025 10:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1040 hrs on 30 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 30-Apr-2025 10:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126789PRICES SUBJECT TO REVIEW30/04/2025 10:35:23 AM

[EventId:202504301040_review] Prices for interval 30-Apr-2025 10:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1035 hrs on 30 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 30-Apr-2025 10:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126782MARKET INTERVENTION29/04/2025 03:58:11 PM

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126779

In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 29/04/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0830 hrs 30/04/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1830 hrs 30/04/2025.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     