127347RESERVE NOTICE01/06/2025 05:40:16 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region on 01/06/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 01/06/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.

The Actual LOR1 condition is forecast to exist until 1830 hrs.

The forecast capacity reserve requirement is 1694 MW.
The minimum capacity reserve available is 1568 MW.


Manager NEM Real Time Operations
     
127341NON-CONFORMANCE31/05/2025 12:50:15 PM

NON-CONFORMANCE Region QLD1 Saturday, 31 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 31 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 31/05/2025 12:30 to 31/05/2025 12:50
Amount: 10 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
127340NON-CONFORMANCE30/05/2025 11:00:14 PM

NON-CONFORMANCE Region QLD1 Friday, 30 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 30 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 30/05/2025 22:25 to 30/05/2025 23:00
Amount: -32 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
127337NON-CONFORMANCE30/05/2025 01:00:13 PM

NON-CONFORMANCE Region QLD1 Friday, 30 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 30 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 30/05/2025 11:50 to 30/05/2025 13:00
Amount: -63 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
127326NON-CONFORMANCE28/05/2025 06:00:15 PM

NON-CONFORMANCE Region QLD1 Wednesday, 28 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 28 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 28/05/2025 17:55 to 28/05/2025 18:00
Amount: -20 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
127322NON-CONFORMANCE28/05/2025 03:15:14 PM

NON-CONFORMANCE Region QLD1 Wednesday, 28 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 28 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 28/05/2025 12:30 to 28/05/2025 15:15
Amount: 26 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
127321NON-CONFORMANCE28/05/2025 02:35:19 AM

NON-CONFORMANCE Region QLD1 Wednesday, 28 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 28 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 28/05/2025 01:35 to 28/05/2025 02:35
Amount: 24 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
127155NON-CONFORMANCE22/05/2025 12:25:17 PM

NON-CONFORMANCE Region NSW1 Thursday, 22 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 22 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MP2
Duration: 22/05/2025 12:05 to 22/05/2025 12:25
Amount: 32 MW
Constraint: NC-N_MP2

Auto-generated on behalf of Manager NEM Real Time Operations
     
127119NON-CONFORMANCE18/05/2025 02:10:18 PM

NON-CONFORMANCE Region SA1 Sunday, 18 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Sunday, 18 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: ADPBA1
Duration: 18/05/2025 13:30 to 18/05/2025 14:10
Amount: 6 MW
Constraint: NC-S_ADPBA1

Auto-generated on behalf of Manager NEM Real Time Operations
     