Planned System Maintenance - Declared Wholesale Gas Market (DWGM)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Declared Wholesale Gas Market
Change Title: Planned System Maintenance - Declared Wholesale Gas Market (DWGM)
Change Start Date & Time: 18/02/2025 09:00:00
Change End Date & Time: 18/02/2025 21:00:00
Outage Start Date & Time: 18/02/2025 18:30:00
Outage End Date & Time: 18/02/2025 20:30:00
Environment: Production
Participant Impact and Requirements: DWGM market system (Webexchanger and MIBB) outage due to planned maintenance.
The following impacts are expected during the maintenance activities:
- All access to the Declared Wholesale Gas Market Production Systems will be unavailable.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
[EventId:202502141235_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 14 February 2025 12:35
Issued by Australian Energy Market Operator Ltd at 1235 hrs on 14 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 February 2025.
Refer to market notice: 124657
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1235 hrs on 14 February 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202502141200_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 14 February 2025 12:00
Issued by Australian Energy Market Operator Ltd at 1200 hrs on 14 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 14 February 2025.
Refer to market notice: 124656
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1200 hrs on 14 February 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202502141050_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 14 February 2025 10:50
Issued by Australian Energy Market Operator Ltd at 1050 hrs on 14 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1050 hrs on 14 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502141015_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 14 February 2025 10:15
Issued by Australian Energy Market Operator Ltd at 1015 hrs on 14 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 14 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1015 hrs on 14 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502141000_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 14 February 2025 10:00
Issued by Australian Energy Market Operator Ltd at 1000 hrs on 14 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 14 February 2025.
Refer to market notice: 124653
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1000 hrs on 14 February 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202502140905_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 14 February 2025 09:05
Issued by Australian Energy Market Operator Ltd at 0905 hrs on 14 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 14 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0905 hrs on 14 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Cancellation of Forecast Minimum System Load (MSL) MSL1 event in the Vic Region on 16/02/2025
Cancellation - Forecast MSL1 - VIC Region at 1400 hrs 13/02/2025.
Refer to Market Notice 124560 for MSL1.
AEMO Operations
Cancellation of Actual (LOR1) condition in the SA region - 12/02/2025
Cancellation of Actual (LOR1) condition in the SA region - 12/02/2025
The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.124572 is cancelled at 2040 hrs 12/02/2025.
Manager NEM Real Time Operations