125621INTER-REGIONAL TRANSFER14/03/2025 06:03:13 AM

Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 14/03/2025

At 0457 hrs 14/03/2025 there was an unplanned outage of Hummocks - Waterloo 132 kV line.

The following constraint set(s) invoked at 0505 hrs 14/03/2025
S-HUWT

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125620INTER-REGIONAL TRANSFER14/03/2025 06:03:11 AM

Inter-regional transfer limit variation - Hummocks - Bungama 132 kV line - SA region - 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hummocks - Bungama 132 kV line - SA region - 14/03/2025

At 0457 hrs 14/03/2025 there was an unplanned outage of Hummocks - Bungama 132 kV line.

The following constraint set(s) invoked at 0505 hrs 14/03/2025
S-HUBG

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125608SETTLEMENTS RESIDUE13/03/2025 06:30:23 PM

[EventId:202503131830_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 March 2025 18:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 13 March 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 March 2025.

Refer to market notice: 125605

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1830 hrs on 13 March 2025.

This is an AEMO autogenerated Market Notice.
     
125605SETTLEMENTS RESIDUE13/03/2025 05:40:23 PM

[EventId:202503131740_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 March 2025 17:40

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1740 hrs on 13 March 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 March 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1740 hrs on 13 March 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
125599RESERVE NOTICE13/03/2025 03:02:59 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/03/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1700 hrs to 1930 hrs 16/03/2025.
The forecast capacity reserve requirement is 1728 MW.
The minimum capacity reserve available is 1129 MW.

AEMO Operations
     
125598RESERVE NOTICE13/03/2025 03:02:59 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/03/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1730 hrs to 1900 hrs 15/03/2025.
The forecast capacity reserve requirement is 1613 MW.
The minimum capacity reserve available is 1540 MW.

AEMO Operations
     
125596NON-CONFORMANCE13/03/2025 01:40:18 PM

NON-CONFORMANCE Region NSW1 Thursday, 13 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 13 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: NEWENSF2
Duration: 13/03/2025 10:40 to 13/03/2025 13:40
Amount: 62 MW
Constraint: NC-N_NEWENSF2

Auto-generated on behalf of Manager NEM Real Time Operations
     
125595NON-CONFORMANCE13/03/2025 01:40:18 PM

NON-CONFORMANCE Region NSW1 Thursday, 13 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 13 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: NEWENSF1
Duration: 13/03/2025 10:40 to 13/03/2025 13:40
Amount: 68 MW
Constraint: NC-N_NEWENSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
125592NON-CONFORMANCE13/03/2025 07:00:17 AM

NON-CONFORMANCE Region QLD1 Thursday, 13 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 13 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 13/03/2025 06:55 to 13/03/2025 07:00
Amount: -67 MW
Constraint: NC-Q_MPP_1