127397RESERVE NOTICE04/06/2025 07:40:01 PM

Cancellation of Actual (LOR1) condition in the QLD region - 04/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 04/06/2025

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.127394 is cancelled at 1945 hrs 04/06/2025.

Manager NEM Real Time Operations
     
127395RESERVE NOTICE04/06/2025 06:47:22 PM

Cancellation of Actual (LOR1) condition in the NSW region - 04/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 04/06/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.127393 is cancelled at 1845 hrs 04/06/2025.

Manager NEM Real Time Operations
     
127394RESERVE NOTICE04/06/2025 06:14:34 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 04/06/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 04/06/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 730 MW
The minimum capacity reserve available is 682 MW

Manager NEM Real Time Operations
     
127393RESERVE NOTICE04/06/2025 05:41:44 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 04/06/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 04/06/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs

The capacity reserve requirement is 1540 MW
The minimum capacity reserve available is 1540 MW

Manager NEM Real Time Operations
     
127392RESERVE NOTICE04/06/2025 05:21:55 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 04/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Periods:


[1.] From 1800 hrs 04/06/2025 to 1900 hrs 04/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 710 MW.


[2.] From 1800 hrs 05/06/2025 to 1900 hrs 05/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 716 MW.


Manager NEM Real Time Operations
     
127390RESERVE NOTICE04/06/2025 04:29:35 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 127382 has been updated at 1600 hrs to the following:


[1.] From 1800 hrs 05/06/2025 to 1900 hrs 05/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 705 MW.


Manager NEM Real Time Operations
     
127389MARKET INTERVENTION04/06/2025 03:57:55 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 127387


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1600 hrs 05/06/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 2300 hrs 05/06/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 06/06/2025 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
127388MARKET INTERVENTION04/06/2025 03:57:47 PM

Direction - SA region 05/06/2025

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 05/06/2025

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 05/06/2025.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
127387MARKET INTERVENTION04/06/2025 02:54:00 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 127383

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2300 hrs 05/06/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 04/06/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm