CHG0101606 - Planned Maintenance to Brisbane Marketnet Site to Site VPN Router
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Market VPN
Change Title: Planned Maintenance to Brisbane Marketnet Site to Site VPN Router
Change Start Date & Time: 22/03/2025 12:00:21
Change End Date & Time: 22/03/2025 14:00:21
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned maintenance:
IPWAN Participants - Nil
Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10 for Policy Based VPN's or 202.44.76.12 for Route Based VPN) only - All L2L connections should be established to both QLD / NSW.
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10 or 202.44.78.12) prior to this scheduled outage. *** Failure to do so will impact connectivity to Marketnet Services ***.
B2B VPN - Nil
SSL VPN Participants: Nil
GASHUB: Nil
Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/03/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 125699 is cancelled at 1415 hrs.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/03/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 125697 has been updated at 1045 hrs to the following:
From 1700 hrs 16/03/2025 to 1830 hrs 16/03/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 656 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/03/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 16/03/2025 to 1800 hrs 16/03/2025.
The forecast capacity reserve requirement is 1105 MW.
The minimum capacity reserve available is 1017 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Lennox Head - Suffolk Park 9G3 132 kV Line - NSW region - 14/03/2025
Inter-regional transfer limit variation - Lennox Head - Suffolk Park 9G3 132 kV Line - NSW region - 14/03/2025
At 1647 hrs 14/03/2025 there was a short notice outage of Lennox Head - Suffolk Park 9G3 132 kV Line.
The following constraint set(s) invoked at 1700 hrs 14/03/2025
N-BAMB_132_OPEN
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
CHG0101257 - Frequency Performance Payments Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Frequency Performance Payments Engine
Change Title: Frequency Performance Payments Release
Change Start Date & Time: 19/03/2025 08:00:00
Change End Date & Time: 20/03/2025 16:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Delivery of Frequency Performance Payments (FPP) calculation results via the participant data model may be periodically delayed during the change window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/03/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 125624 is cancelled at 1200 hrs 14/03/2025.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/03/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 125622 has been updated at 1000 hrs 14/03/2025 to the following:
From 1730 hrs to 1830 hrs 16/03/2025.
The forecast capacity reserve requirement is 1019 MW.
The minimum capacity reserve available is 845 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/03/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1730 hrs 16/03/2025 to 1830 hrs 16/03/2025.
The forecast capacity reserve requirement is 1112 MW.
The minimum capacity reserve available is 1064 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations