124585RESERVE NOTICE13/02/2025 06:45:48 AM

PDPASA - Suspect Lack Of Reserve Level 2 (LOR2) in the QLD Region on 13/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO considers that there is a suspect Forecast LOR2 condition for the QLD region for the following period[s]:

[1.] From 1830 hrs 13/02/2025 to 1930 hrs 13/02/2025.
The forecast capacity reserve requirement is 639 MW.
The minimum capacity reserve available is 480 MW.

AEMO is currently investigating this LOR2 forecast condition to confirm whether they are valid.

Manager NEM Real Time Operations
     
124579RESERVE NOTICE12/02/2025 08:44:30 PM

Cancellation of Actual (LOR1) condition in the SA region - 12/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the SA region - 12/02/2025

The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.124572 is cancelled at 2040 hrs 12/02/2025.

Manager NEM Real Time Operations
     
124572RESERVE NOTICE12/02/2025 06:53:15 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 12/02/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 12/02/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1830 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 524 MW
The minimum capacity reserve available is 470 MW

Manager NEM Real Time Operations
     
124477INTER-REGIONAL TRANSFER11/02/2025 11:27:16 PM

Inter-regional transfer limit variation - Armidale No 1 SVC- NSW region - 11/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale No 1 SVC - NSW region - 11/02/2025

At 2315 hrs 11/02/2025 there was an unplanned outage of Armidale No 1 SVC.

The following constraint set(s) invoked at 2325 hrs 11/02/2025
N-AR_VC1

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
124472INTER-REGIONAL TRANSFER11/02/2025 06:00:41 PM

Inter-regional transfer limit variation - Yass Overload Control Scheme - NSW region - 11/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Yass Overload Control Scheme - NSW region - 11/02/2025

At 1750 hrs 11/02/2025 there was a short notice outage of Yass Overload Control Scheme.

The following constraint set(s) invoked at 1750 hrs: N-YSWG_SCHEME

This constraint set(s) contains equations with the following interconnectors on the LHS,
V-S-MNSP1
VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
124469INTER-REGIONAL TRANSFER11/02/2025 03:59:36 PM

Inter-regional transfer limit variation - MLTS-SMTS No1 500 kV line CB at SYTS - VIC region - 11/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - MLTS-SMTS No1 500 kV line CB at SYTS - VIC region - 11/02/2025

At 1538 hrs 11/02/2025 there was an unplanned outage of MLTS-SMTS No1 500 kV line CB at SYTS .

The following constraint set(s) invoked at 1600 hrs 11/02/2025
V-SY_CB

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
124468INTER-REGIONAL TRANSFER11/02/2025 03:40:29 PM

Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 11/02/2025

AEMO ELECTRICITY MARKET NOTICE

Referring to Market Notice 124466.

The power system security condition in the SA region, requiring AEMO to invoke the automated constraint set CA_SYDS_56BD5936 has ended at 1520 hrs.

Constraint set revoked: CA_SYDS_56BD5936

Manager NEM Real Time Operations
     
124466INTER-REGIONAL TRANSFER11/02/2025 02:19:04 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 11/02/2025

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the SA region, AEMO has invoked automated constraint set CA_SYDS_56BD5936 from 1410 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

V-SA

Manager NEM Real Time Operations
     
124465MARKET SYSTEMS11/02/2025 02:04:53 PM

CHG0100111 | Completed | Pre-Production | Pre-Prod eMDM February Maintenance Release

Change Number: CHG0100111

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: MDM - Meter Data Management_PreProd

Change Title: Pre-Prod eMDM February Maintenance Release

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm