Cancellation of Actual (LOR1) condition in the NSW region - 15/01/2025
Cancellation of Actual (LOR1) condition in the NSW region - 15/01/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.123289 is cancelled at 1515 hrs 15/01/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/01/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/01/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1430 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1430 MW
The minimum capacity reserve available is 744 MW
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Murray - Lower Tumut 330 kV 66 line - NSW region - 15/01/2025
Inter-regional transfer limit variation - Murray - Lower Tumut 330 kV 66 line - NSW region - 15/01/2025
At 1400 hrs 15/01/2025 there was an unplanned outage of Murray - Lower Tumut 330 kV 66 line.
The following constraint set(s) invoked at 1415 hrs 15/01/2025
I-LTMS
This constraint set(s) contains equations with the following interconnectors on the LHS.
VIC1-NSW1,V-S-MNSP1,NSW1-QLD1,T-V-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Lower Tumut - Yass 330 kV 03 Line - NSW region - 15/01/2025
Inter-regional transfer limit variation - Lower Tumut - Yass 330 kV 03 Line - NSW region - 15/01/2025
At 1358 hrs 15/01/2025 there was an unplanned outage of Lower Tumut - Yass 330 kV 03 Line.
The following constraint set(s) invoked at 1400 hrs 15/01/2025
N-X_LTYS_MNYS
This constraint set(s) contains equations with the following interconnectors on the LHS.
VIC1-NSW1,N-Q-MNSP1,NSW1-QLD1,V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Muswellbrook 330/132 kV Transformer 1 - NSW region - 15/01/2025
Inter-regional transfer limit variation - Muswellbrook 330/132 kV Transformer 1 - NSW region - 15/01/2025
At 1337 hrs 15/01/2025 there was an unplanned outage of Muswellbrook 330/132 kV Transformer 1.
The following constraint set(s) invoked at 1355 hrs 15/01/2025
N-MUTW_88
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,T-V-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 14/01/2025
Cancellation of Actual (LOR1) condition in the NSW region - 14/01/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.123221 is cancelled at 1845 hrs 14/01/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/01/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/01/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1629 MW
The minimum capacity reserve available is 1330 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 13/01/2025
Cancellation of Actual (LOR1) condition in the NSW region - 13/01/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.123180 is cancelled at 2045 hrs 13/01/2025.
Manager NEM Real Time Operations
Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025
Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025
Refer market notice: 123171
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 2000 hrs.
The forecast capacity reserve requirement is 1365 MW.
The minimum capacity reserve available is 966 MW.
Manager NEM Real Time Operations