125619RESERVE NOTICE14/03/2025 04:54:36 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/03/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 125607 is cancelled at 0450 hrs 14/03/2025.

No LOR2 condition is currently forecast in the STPASA period.

Manager NEM Real Time Operations
     
125608SETTLEMENTS RESIDUE13/03/2025 06:30:23 PM

[EventId:202503131830_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 March 2025 18:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 13 March 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 March 2025.

Refer to market notice: 125605

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1830 hrs on 13 March 2025.

This is an AEMO autogenerated Market Notice.
     
125607RESERVE NOTICE13/03/2025 06:27:48 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/03/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1700 hrs 16/03/2025 to 1830 hrs 16/03/2025.
The forecast capacity reserve requirement is 1154 MW.
The minimum capacity reserve available is 948 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
125605SETTLEMENTS RESIDUE13/03/2025 05:40:23 PM

[EventId:202503131740_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 March 2025 17:40

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1740 hrs on 13 March 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 March 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1740 hrs on 13 March 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
125524GENERAL NOTICE11/03/2025 01:51:14 PM

NEM Local Temperature Alerts for SA, VIC from 11 Mar 2025 to 15 Mar 2025

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Port Augusta Ap (39+ Deg C): 14th Mar, 15th Mar

VIC
Latrobe Valley Ap (39+ Deg C): 15th Mar
Mildura Ap (39+ Deg C): 14th Mar, 15th Mar

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
125516SETTLEMENTS RESIDUE11/03/2025 09:30:23 AM

[EventId:202503110930_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 11 March 2025 09:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0930 hrs on 11 March 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 March 2025.

Refer to market notice: 125514

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 0930 hrs on 11 March 2025.

This is an AEMO autogenerated Market Notice.
     
125514SETTLEMENTS RESIDUE11/03/2025 08:30:33 AM

[EventId:202503110830_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 11 March 2025 08:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0830 hrs on 11 March 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 March 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0830 hrs on 11 March 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
125513PRICES UNCHANGED11/03/2025 08:20:19 AM

[EventId:202503110755_confirmed] Prices for interval 11-Mar-2025 07:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0820 hrs on 11 March 2025

PRICES ARE NOW CONFIRMED for trading interval 11-Mar-2025 07:55.

In accordance with Market Notice 125502 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125512PRICES UNCHANGED11/03/2025 08:20:19 AM

[EventId:202503110820_confirmed] Prices for interval 11-Mar-2025 08:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0820 hrs on 11 March 2025

PRICES ARE NOW CONFIRMED for trading interval 11-Mar-2025 08:20.

In accordance with Market Notice 125507 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.