CHG0101606 - Planned Maintenance to Brisbane Marketnet Site to Site VPN Router
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Market VPN
Change Title: Planned Maintenance to Brisbane Marketnet Site to Site VPN Router
Change Start Date & Time: 22/03/2025 12:00:21
Change End Date & Time: 22/03/2025 14:00:21
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned maintenance:
IPWAN Participants - Nil
Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10 for Policy Based VPN's or 202.44.76.12 for Route Based VPN) only - All L2L connections should be established to both QLD / NSW.
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10 or 202.44.78.12) prior to this scheduled outage. *** Failure to do so will impact connectivity to Marketnet Services ***.
B2B VPN - Nil
SSL VPN Participants: Nil
GASHUB: Nil
Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
[EventId:202503171645_confirmed] Prices for interval 17-Mar-2025 16:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 17 March 2025
PRICES ARE NOW CONFIRMED for trading interval 17-Mar-2025 16:45.
In accordance with Market Notice 125760 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503171700_confirmed] Prices for interval 17-Mar-2025 17:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 17 March 2025
PRICES ARE NOW CONFIRMED for trading interval 17-Mar-2025 17:00.
In accordance with Market Notice 125764 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503171655_confirmed] Prices for interval 17-Mar-2025 16:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 17 March 2025
PRICES ARE NOW CONFIRMED for trading interval 17-Mar-2025 16:55.
In accordance with Market Notice 125763 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503171650_confirmed] Prices for interval 17-Mar-2025 16:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 17 March 2025
PRICES ARE NOW CONFIRMED for trading interval 17-Mar-2025 16:50.
In accordance with Market Notice 125762 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503171640_confirmed] Prices for interval 17-Mar-2025 16:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 17 March 2025
PRICES ARE NOW CONFIRMED for trading interval 17-Mar-2025 16:40.
In accordance with Market Notice 125759 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503171635_confirmed] Prices for interval 17-Mar-2025 16:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 17 March 2025
PRICES ARE NOW CONFIRMED for trading interval 17-Mar-2025 16:35.
In accordance with Market Notice 125758 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Cancellation of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE
Cancellation time: 17/03/2025 14:29
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 125745
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV
Cancellation time: 17/03/2025 14:29
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 125744
Auto-generated on behalf of Manager NEM Real Time Operations