Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 11/02/2025
Referring to Market Notice 124466.
The power system security condition in the SA region, requiring AEMO to invoke the automated constraint set CA_SYDS_56BD5936 has ended at 1520 hrs.
Constraint set revoked: CA_SYDS_56BD5936
Manager NEM Real Time Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 16/02/2025
Update to Market Notice 124437 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 16/02/2025.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 2115 MW
o MSL2 - 1615 MW
o MSL3 - 1115 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1200 hrs to 1500 hrs 16/02/2025. Minimum regional demand is forecast to be 1873 MW at 1330 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 11/02/2025
In order to maintain the power system in a secure operating state in the SA region, AEMO has invoked automated constraint set CA_SYDS_56BD5936 from 1410 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
V-SA
Manager NEM Real Time Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 16/02/2025
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 16/02/2025.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 2060 MW
o MSL2 - 1560 MW
o MSL3 - 1060 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1430 hrs 16/02/2025. Minimum regional demand is forecast to be 1838 MW at 1330 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
Inter-regional transfer limit variation - Ingleburn - Wallerawang (77) 330 kV line - NSW region - 10/02/2025
Inter-regional transfer limit variation - Ingleburn - Wallerawang (77) 330 kV line - NSW region - 10/02/2025
At 0945 hrs 10/02/2025 there was an unplanned outage of Ingleburn - Wallerawang (77) 330 kV line.
The following constraint set(s) invoked at 0955 hrs 10/02/2025
N-X_AVMA_SSWW
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Update - Non-credible contingency event - NSW region - 23/01/2025
Update - Non-credible contingency event - NSW region - 23/01/2025
Refer AEMO Electricity Market Notice 123615
At 0240 hrs on the 23/01/2025 there was a trip and auto reclose of the Kempsey - Macksville 9W5 and the Kempsey - Raleigh 9W2 132kV Lines
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Collector - Marulan (4) 330 kV line - NSW region - 06/02/2025
Inter-regional transfer limit variation -Collector - Marulan (4) 330 kV line - NSW region - 06/02/2025
The outage has been completed and Collector - Marulan (4) 330 kV line returned to service at 0825 hrs 06/02/2025
Constraint set(s) revoked: N-CTMN_4_WG_CLOSE
Manager NEM Real Time Operations
Update - Non-credible contingency event - TAS region - 03/02/2025
Update - Non-credible contingency event - TAS region - 03/02/2025
Refer AEMO Electricity Market Notice 124044
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will cancel the reclassification of this event as a credible contingency event.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Collector WF to Marulan No. 4 330 kV Line - NSW region - 04/02/2025
Inter-regional transfer limit variation - Collector WF to Marulan No. 4 330 kV Line - NSW region - 04/02/2025
A planned outage of Collector WF to Marulan No. 4 330 kV Line in the NSW region was scheduled from 0600 hrs 02/02/2025 to 1600 hrs 19/02/2025.
The outage has been completed and Collector WF to Marulan No. 4 330 kV Line returned to service at 1710 hrs 04/02/2025
Constraint set(s) revoked: N-CTMN_4_WG_CLOSE
Manager NEM Real Time Operations