Market Notices

125654RESERVE NOTICE14/03/2025 06:40:25 PM

Cancellation of Actual (LOR1) condition in the NSW region - 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 14/03/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.125652 is cancelled at 1840 hrs 14/03/2025.

Manager NEM Real Time Operations
     
125652RESERVE NOTICE14/03/2025 05:41:45 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/03/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs

The capacity reserve requirement is 1699 MW
The minimum capacity reserve available is 1528 MW

Manager NEM Real Time Operations
     
125647INTER-REGIONAL TRANSFER14/03/2025 05:11:12 PM

Inter-regional transfer limit variation - Lennox Head - Suffolk Park 9G3 132 kV Line - NSW region - 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Lennox Head - Suffolk Park 9G3 132 kV Line - NSW region - 14/03/2025

At 1647 hrs 14/03/2025 there was a short notice outage of Lennox Head - Suffolk Park 9G3 132 kV Line.

The following constraint set(s) invoked at 1700 hrs 14/03/2025
N-BAMB_132_OPEN

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125621INTER-REGIONAL TRANSFER14/03/2025 06:03:13 AM

Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 14/03/2025

At 0457 hrs 14/03/2025 there was an unplanned outage of Hummocks - Waterloo 132 kV line.

The following constraint set(s) invoked at 0505 hrs 14/03/2025
S-HUWT

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125620INTER-REGIONAL TRANSFER14/03/2025 06:03:11 AM

Inter-regional transfer limit variation - Hummocks - Bungama 132 kV line - SA region - 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hummocks - Bungama 132 kV line - SA region - 14/03/2025

At 0457 hrs 14/03/2025 there was an unplanned outage of Hummocks - Bungama 132 kV line.

The following constraint set(s) invoked at 0505 hrs 14/03/2025
S-HUBG

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125609RESERVE NOTICE13/03/2025 06:41:32 PM

Cancellation of Actual (LOR1) condition in the NSW region - 13/03/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 13/03/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.125606 is cancelled at 1840 hrs 13/03/2025.

Manager NEM Real Time Operations
     
125606RESERVE NOTICE13/03/2025 05:45:09 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/03/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/03/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs

The capacity reserve requirement is 1668 MW
The minimum capacity reserve available is 1530 MW

Manager NEM Real Time Operations
     
125568POWER SYSTEM EVENTS12/03/2025 03:00:00 PM

Update - Non-credible contingency event - TAS region - 12/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 12/03/2025

Refer AEMO Electricity Market Notice 125564

The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.

Region: TAS

Elements: Ulverstone - Emu Bay 110kV Line and the Ulverstone - Sheffield tee Paloona 110kV Line
Duration: 1500 hrs 12/03/2025 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
     
125566POWER SYSTEM EVENTS12/03/2025 02:58:09 PM

Update - Non-credible contingency event - TAS region - 12/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 12/03/2025

Refer AEMO Electricity Market Notice 125556

The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.

Region: TAS

Elements: Sheffield - Burnie No. 1 220kV Line, Sheffield - Burnie No. 2 110kV Line and the Ulverstone - Emu Bay 110kV Line
Duration: 1400 hrs 12/03/2025 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
     