Non-credible contingency event - NSW region - 07/03/2025
Non-credible contingency event - NSW region - 07/03/2025
At 0612 hrs the following plant tripped.
Lismore132 - Mullumbimby 9U6 132kV Line
Lismore132 - Mullumbimby 9U7 132kV Line
Ewingsdale - Mullumbimby 9G5 132kV Line
No 1 and 2 cables of Directlink
AEMO did not instruct load shedding.
Approximately 7MW of bulk electrical load has been disconnected.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 7 March 2025
NON-CONFORMANCE QLD1 Region Friday, 7 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: CPP_4
Duration: 07/03/2025 00:30 to 07/03/2025 01:00
Amount: -21 MW
Constraint: NC-Q_CPP_4
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202503061820_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 06 March 2025 18:20
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 6 March 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 6 March 2025.
Refer to market notice: 125341
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1820 hrs on 6 March 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202503061600_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 06 March 2025 16:00
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 6 March 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 6 March 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1600 hrs on 6 March 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region VIC1 Thursday, 6 March 2025
NON-CONFORMANCE VIC1 Region Thursday, 6 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MOKOSF1
Duration: 06/03/2025 13:20 to 06/03/2025 13:35
Amount: 9 MW
Constraint: NC-V_MOKOSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NEM Local Temperature Alerts for SA from 06 Mar 2025 to 10 Mar 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Port Augusta Ap (39+ Deg C): 10th Mar
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
[EventId:202503051905_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 05 March 2025 19:05
Issued by Australian Energy Market Operator Ltd at 1905 hrs on 5 March 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 5 March 2025.
Refer to market notice: 125282
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1905 hrs on 5 March 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202503051805_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 05 March 2025 18:05
Issued by Australian Energy Market Operator Ltd at 1805 hrs on 5 March 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 5 March 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1805 hrs on 5 March 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region QLD1 Wednesday, 5 March 2025
NON-CONFORMANCE QLD1 Region Wednesday, 5 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 05/03/2025 17:35 to 05/03/2025 17:45
Amount: -12 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations