CHG0101808 - Pre-production EMMS database Maintainence activity
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Data Store
Change Title: Pre-production EMMS database Maintainence activity
Change Start Date & Time: 11/03/2025 01:00:00
Change End Date & Time: 19/03/2025 17:00:00
Outage Start Date & Time: 13/03/2025 12:00:00
Outage End Date & Time: 13/03/2025 15:00:00
Environment: Pre-Production
Participant Impact and Requirements: The Electricity Market Management System (EMMS) , Gas Supply Hub (GSH) and FPP Pre-Production environment will be unavailable during the outage window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
NON-CONFORMANCE Region QLD1 Thursday, 13 March 2025
NON-CONFORMANCE QLD1 Region Thursday, 13 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 13/03/2025 06:55 to 13/03/2025 07:00
Amount: -67 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
CHG0101808 - Pre-production EMMS database Maintainence activity
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Data Store
Change Title: Pre-production EMMS database Maintainence activity
Change Start Date & Time: 11/03/2025 01:00:00
Change End Date & Time: 19/03/2025 17:00:00
Outage Start Date & Time: 13/03/2025 12:00:00
Outage End Date & Time: 13/03/2025 15:00:00
Environment: Pre-Production
Participant Impact and Requirements: The Electricity Market Management System (EMMS) , Gas Supply Hub (GSH) and FPP Pre-Production environment will be unavailable during the outage window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
NON-CONFORMANCE Region NSW1 Wednesday, 12 March 2025
NON-CONFORMANCE NSW1 Region Wednesday, 12 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 12/03/2025 17:30 to 12/03/2025 17:35
Amount: 16 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
CHG0101876 - Pre-Prod eMDM Hotfix Maintenance Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM Hotfix Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Update - Non-credible contingency event - TAS region - 12/03/2025
Update - Non-credible contingency event - TAS region - 12/03/2025
Refer AEMO Electricity Market Notice 125564
The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.
Region: TAS
Elements: Ulverstone - Emu Bay 110kV Line and the Ulverstone - Sheffield tee Paloona 110kV Line
Duration: 1500 hrs 12/03/2025 until further notice
Constraint set(s) invoked: Nil
Manager NEM Real Time Operations
CHG0101704 - As part of the Platform Services Patching Program, webMethods Inactive Production Application Servers in Brisban
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Business to Business data exchange
Change Title: As part of the Platform Services Patching Program, webMethods Inactive Production Application Servers in Brisbane will have critical security patches applied.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Update - Non-credible contingency event - TAS region - 12/03/2025
Update - Non-credible contingency event - TAS region - 12/03/2025
Refer AEMO Electricity Market Notice 125556
The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.
Region: TAS
Elements: Sheffield - Burnie No. 1 220kV Line, Sheffield - Burnie No. 2 110kV Line and the Ulverstone - Emu Bay 110kV Line
Duration: 1400 hrs 12/03/2025 until further notice
Constraint set(s) invoked: Nil
Manager NEM Real Time Operations
Non-credible contingency event - TAS region - 12/03/2025
Non-credible contingency event - TAS region - 12/03/2025
At 1303 hrs the Ulverstone - Emu Bay 110kV Line and the Ulverstone - Sheffield tee Paloona 110kV Line tripped and auto reclosed.
AEMO did not instruct load shedding.
Approximately 12MW of bulk electrical load was disconnected momentarily.
The cause of this non credible contingency event is not known at this stage.