Market Notices

124986INTER-REGIONAL TRANSFER22/02/2025 08:11:27 AM

Inter-regional transfer limit variation - Collector Windfarm - Yass (3L) 330 kV line - NSW region - 22/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Collector Windfarm - Yass (3L) 330 kV line - NSW region - 22/02/2025

A planned outage of Collector Windfarm - Yass (3L) 330 kV line in the NSW region was scheduled from 0600 hrs 17/02/2025 to 1600 hrs 24/02/2025.

The outage has been completed and Collector Windfarm - Yass (3L) 330 kV line returned to service at 0746 hrs 22/02/2025

Constraint set(s) revoked: N-CTYS_3L_WG_CLOSE

Manager NEM Real Time Operations
     
124971NON-CONFORMANCE21/02/2025 12:10:28 PM

NON-CONFORMANCE Region VIC1 Friday, 21 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Friday, 21 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MCKAY1
Duration: 21/02/2025 12:00 to 21/02/2025 12:10
Amount: -54 MW
Constraint: NC-V_MCKAY1

Auto-generated on behalf of Manager NEM Real Time Operations
     
124969NON-CONFORMANCE21/02/2025 12:05:21 PM

NON-CONFORMANCE Region SA1 Friday, 21 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Friday, 21 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BLYTHB1
Duration: 21/02/2025 11:50 to 21/02/2025 12:05
Amount: -19 MW
Constraint: NC-S_BLYTHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
124965NON-CONFORMANCE21/02/2025 10:20:19 AM

NON-CONFORMANCE Region QLD1 Friday, 21 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 21 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GANGARR1
Duration: 21/02/2025 09:40 to 21/02/2025 10:20
Amount: 72 MW
Constraint: NC-Q_GANGARR1

Auto-generated on behalf of Manager NEM Real Time Operations
     
124958SETTLEMENTS RESIDUE20/02/2025 06:30:26 PM

[EventId:202502201830_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 20 February 2025 18:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 20 February 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 20 February 2025.

Refer to market notice: 124950

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1830 hrs on 20 February 2025.

This is an AEMO autogenerated Market Notice.
     
124950SETTLEMENTS RESIDUE20/02/2025 05:35:31 PM

[EventId:202502201735_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 20 February 2025 17:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1735 hrs on 20 February 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 20 February 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1735 hrs on 20 February 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
124941NON-CONFORMANCE20/02/2025 02:25:16 PM

NON-CONFORMANCE Region NSW1 Thursday, 20 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 20 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: CAPBES1
Duration: 20/02/2025 14:15 to 20/02/2025 14:25
Amount: 70 MW
Constraint: NC-N_CAPBES1

Auto-generated on behalf of Manager NEM Real Time Operations
     
124914NON-CONFORMANCE20/02/2025 07:55:28 AM

NON-CONFORMANCE Region SA1 Thursday, 20 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Wednesday, 19 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: CLEMGPWF
Duration: 19/02/2025 17:30 to 20/02/2025 07:55
Amount: 15 MW
Constraint: NC-S_CLEMGPWF

Auto-generated on behalf of Manager NEM Real Time Operations
     
124913NON-CONFORMANCE20/02/2025 03:45:14 AM

NON-CONFORMANCE Region NSW1 Thursday, 20 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 20 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 20/02/2025 03:30 to 20/02/2025 03:45
Amount: -8 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     