124084SETTLEMENTS RESIDUE04/02/2025 02:42:10 PM

[EventId:202502041335_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 04 February 2025 13:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1335 hrs on 4 February 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 4 February 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1335 hrs on 4 February 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
124077MARKET SYSTEMS04/02/2025 02:17:21 PM

CHG0101137 | Completed | Production | Planned Maintenance to Norwest Marketnet Site to Site VPN Router

Change Number: CHG0101137

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Local Area Network

Change Title: Planned Maintenance to Norwest Marketnet Site to Site VPN Router

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
124069SETTLEMENTS RESIDUE04/02/2025 01:15:58 PM

[EventId:202502041300_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 04 February 2025 13:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 4 February 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 4 February 2025.

Refer to market notice: 124064

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1300 hrs on 4 February 2025.

This is an AEMO autogenerated Market Notice.
     
124064SETTLEMENTS RESIDUE04/02/2025 11:35:33 AM

[EventId:202502041135_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 04 February 2025 11:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1135 hrs on 4 February 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 4 February 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1135 hrs on 4 February 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
124044POWER SYSTEM EVENTS03/02/2025 02:13:15 PM

Update - Non-credible contingency event - TAS region - 03/02/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 03/02/2025

Refer AEMO Electricity Market Notice 124043

The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.

Region: TAS

Elements: Farrell - Reece No.1 and No.2 220 kV lines
Duration: 1410 hrs 03/02/2025 until further notice
Constraint set(s) invoked: F-T-FARE_N-2

Manager NEM Real Time Operations
     
124043POWER SYSTEM EVENTS03/02/2025 02:02:24 PM

Non-credible contingency event - TAS region - 03/02/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 03/02/2025

At 1333 hrs the Farrell - Reece No.1 and No.2 220 kV lines tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
124036MARKET SYSTEMS03/02/2025 09:32:00 AM

CHG0100610 | Completed | Production | Planned Maintenance to Brisbane Internet Router

Change Number: CHG0100610

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Internet Access

Change Title: Planned Maintenance to Brisbane Internet Router

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.

     
123995SETTLEMENTS RESIDUE01/02/2025 06:30:45 PM

[EventId:202502011830_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 01 February 2025 18:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 1 February 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 1 February 2025.

Refer to market notice: 123990

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1830 hrs on 1 February 2025.

This is an AEMO autogenerated Market Notice.
     
123990SETTLEMENTS RESIDUE01/02/2025 05:00:25 PM

[EventId:202502011700_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 01 February 2025 17:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 1 February 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 1 February 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1700 hrs on 1 February 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     