Market Notices

125647INTER-REGIONAL TRANSFER14/03/2025 05:11:12 PM

Inter-regional transfer limit variation - Lennox Head - Suffolk Park 9G3 132 kV Line - NSW region - 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Lennox Head - Suffolk Park 9G3 132 kV Line - NSW region - 14/03/2025

At 1647 hrs 14/03/2025 there was a short notice outage of Lennox Head - Suffolk Park 9G3 132 kV Line.

The following constraint set(s) invoked at 1700 hrs 14/03/2025
N-BAMB_132_OPEN

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125627MARKET SYSTEMS14/03/2025 02:13:15 PM

CHG0101257 - Frequency Performance Payments Release

Change Number: CHG0101257

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Frequency Performance Payments Engine
Change Title: Frequency Performance Payments Release
Change Start Date & Time: 19/03/2025 08:00:00
Change End Date & Time: 20/03/2025 16:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Delivery of Frequency Performance Payments (FPP) calculation results via the participant data model may be periodically delayed during the change window.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
125621INTER-REGIONAL TRANSFER14/03/2025 06:03:13 AM

Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 14/03/2025

At 0457 hrs 14/03/2025 there was an unplanned outage of Hummocks - Waterloo 132 kV line.

The following constraint set(s) invoked at 0505 hrs 14/03/2025
S-HUWT

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125620INTER-REGIONAL TRANSFER14/03/2025 06:03:11 AM

Inter-regional transfer limit variation - Hummocks - Bungama 132 kV line - SA region - 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hummocks - Bungama 132 kV line - SA region - 14/03/2025

At 0457 hrs 14/03/2025 there was an unplanned outage of Hummocks - Bungama 132 kV line.

The following constraint set(s) invoked at 0505 hrs 14/03/2025
S-HUBG

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125593MARKET SYSTEMS13/03/2025 09:28:51 AM

CHG0101808 - Pre-production EMMS database Maintainence activity

Change Number: CHG0101808

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Data Store
Change Title: Pre-production EMMS database Maintainence activity
Change Start Date & Time: 11/03/2025 01:00:00
Change End Date & Time: 19/03/2025 17:00:00
Outage Start Date & Time: 13/03/2025 12:00:00
Outage End Date & Time: 13/03/2025 15:00:00
Environment: Pre-Production
Participant Impact and Requirements: The Electricity Market Management System (EMMS) , Gas Supply Hub (GSH) and FPP Pre-Production environment will be unavailable during the outage window.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
125591MARKET SYSTEMS13/03/2025 06:56:51 AM

CHG0101808 - Pre-production EMMS database Maintainence activity

Change Number: CHG0101808

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Data Store
Change Title: Pre-production EMMS database Maintainence activity
Change Start Date & Time: 11/03/2025 01:00:00
Change End Date & Time: 19/03/2025 17:00:00
Outage Start Date & Time: 13/03/2025 12:00:00
Outage End Date & Time: 13/03/2025 15:00:00
Environment: Pre-Production
Participant Impact and Requirements: The Electricity Market Management System (EMMS) , Gas Supply Hub (GSH) and FPP Pre-Production environment will be unavailable during the outage window.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
125570MARKET SYSTEMS12/03/2025 03:23:40 PM

CHG0101876 - Pre-Prod eMDM Hotfix Maintenance Release

Change Number: CHG0101876

Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM Hotfix Maintenance Release

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
125567MARKET SYSTEMS12/03/2025 02:53:03 PM

CHG0101704 - As part of the Platform Services Patching Program, webMethods Inactive Production Application Servers in Brisban

Change Number: CHG0101704

Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Business to Business data exchange
Change Title: As part of the Platform Services Patching Program, webMethods Inactive Production Application Servers in Brisbane will have critical security patches applied.

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
125560INTER-REGIONAL TRANSFER12/03/2025 02:20:15 PM

Inter-regional transfer limit variation - Directlink Cables 1 and 2 - NSW region - 12/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Directlink Cables 1 and 2 - NSW region - 12/03/2025

An unplanned outage of Directlink Cables 1 and 2 in the NSW region was scheduled to return to service at 1700 hrs 12/03/2025.

The outage has been completed and Directlink Cables 1 and 2 returned to service at 1350 hrs 12/03/2025

Constraint set(s) revoked: N-X_MBTE_3

Manager NEM Real Time Operations
     