Filter by category
Filter by Date
CHG0098666:Telstra Melbourne Indial (03 9609 XXXX-XXXX)
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Cisco IP Phone
Change Title: Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
CHG0098678:Telstra Melbourne Indial (03 9609 XXXX-XXXX)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cisco IP Phone
Change Title: Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)
Change Start Date & Time: 08/10/2024 00:00:00 AEST
Change End Date & Time: 08/10/2024 06:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Outage Duration:
3 x 15 Minutes during the window
Impacts:
Reduced redundancy for Inbound and Outbound Calls (automatically rerouted via Perth).
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0098666 | Production | Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cisco IP Phone
Change Title: Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)
Change Start Date & Time: 08/09/2024 00:00:00 AEST
Change End Date & Time: 08/09/2024 06:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Outage Duration:
3 x 15 Minutes
Impacts:
Reduced redundancy for Inbound and Outbound Calls (automatically rerouted via Perth).
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .
CHG0098660 | Production | Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cisco IP Phone
Change Title: Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)
Change Start Date & Time: 24/09/2024 00:00:00 AEST
Change End Date & Time: 24/09/2024 06:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Outage Duration:
1 x 3 Hours
Impacts:
Reduced redundancy for Inbound and Outbound Calls (automatically rerouted via Perth).
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .
Update - Lightning vulnerable lines in TAS region
Update - Lightning vulnerable lines in TAS region
Refer to AEMO Electricity Market Notice 118320 ,118321, 118322
At 1340 hrs 19/09/2024 the Gordon - Chapel St No 1 220 kV line and the Gordon - Chapel St No 2 220 kV line tripped.
The cause of the trip was identified as due to Lightning.
In accordance with SO_OP_3715, AEMO now considers the Gordon - Chapel St No 1 220 kV line and the Gordon - Chapel St No 2 220 kV line to be vulnerable with a category of Vulnerability due to Lightning.
Manager NEM Real Time Operations
CHG0098562 | Pre-Production | Pre-Production Electricity Market Management System (EMMS) Maintenance - Outages
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: Pre-Production Electricity Market Management System (EMMS) Maintenance - Outages
Change Start Date & Time: 23/09/2024 14:00:00 AEST
Change End Date & Time: 26/09/2024 17:00:00 AEST
Outage Start Date & Time: 24/09/2024 10:00:00 AEST
Outage End Date & Time: 26/09/2024 17:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: This Maintenance activity may cause intermittent outages to below applications during the outage period .
Impacted Systems:
1.EMMS systems (Dispatch/ PASA/ Forecasting/ Settlements)
2.Identity Service will be running only for authentication purposes.
3.Web Portal including menu items (Markets, Internal & Public portal)
4.GSH
5.GBB
6.Any GAS systems that have a NEMA / WARA database connection.
7.MSATS
8.CDR
9.DERR
If any ongoing issues are identified, please contact the AEMO Support Hub 1300 236 600.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Planned outage of Tailem Bend - South East 275 kV transmission line in the South Australia region beginning on 20/09/2024
The Tailem Bend - South East No 1 275 kV line in the South Australian (SA) region is planned to be out of service from 2100 hrs on 20/09/2024 to 0530 hrs on 21/09/2024.
A credible contingency event during this planned outage could cause synchronous separation of the SA region from the rest of the NEM.
During this planned outage:
- Power transfer will be restricted across the VIC - SA interconnector (Heywood interconnector); and
- Post contingent FCAS will be sourced within SA following Separation event.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
CHG0098133 | Production | NEM Reform - RMI (Retail Market Improvements) MSATS 54.0
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Market Settlement & Transfer System
Change Title: NEM Reform - RMI (Retail Market Improvements) MSATS 54.0
Change Start Date & Time: 29/09/2024 10:00:00 AEST
Change End Date & Time: 29/09/2024 17:00:00 AEST
Outage Start Date & Time: 29/09/2024 10:00:00 AEST
Outage End Date & Time: 29/09/2024 14:00:00 AEST
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Cancellation of Actual (LOR1) condition in the NSW region - 16/09/2024
Cancellation of Actual (LOR1) condition in the NSW region - 16/09/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.118298 is cancelled at 1915 hrs 16/09/2024.
Manager NEM Real Time Operations