Filter by category
Filter by Date
Inter-regional transfer limit variation - Lismore-Lismore132 9W1 132kV Line - NSW region - 02/09/2024
Inter-regional transfer limit variation - Lismore-Lismore132 9W1 132kV Line - NSW region - 02/09/2024
At 1516 hrs 02/09/2024 there was an unplanned outage of Lismore-Lismore132 9W1 132kV Line
The following constraint set(s) invoked at 1525 hrs 02/09/2024
N-LSLS_9U8
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 kV Line - NSW region - 02/09/2024
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 kV Line - NSW region - 02/09/2024
A planned outage of Armidale - Sapphire 8E 330 kV Line in the NSW region was scheduled from 1630 hrs 31/08/2024 to 1800 hrs 02/09/2024.
The outage has been rescheduled for 1630 hrs 31/08/2024 to 1200 hrs 03/09/2024.
The following constraint set(s) invoked at 1630 hrs 31/08/2024
N-ARSR_8E, N-DM_SVC, N-TW_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Network Augmentation Commissioned - NSW Region - 01/09/2024
Network Augmentation Commissioned - NSW Region - 01/09/2024
At 2125 hrs. Buronga -Redcliffs X9 220 kV line has been commissioned.
At 2125 hrs. Buronga -Redcliffs OX1 220 kV line has been de-commissioned.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330kv Line- NSW region - 01/09/2024
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330kv Line - NSW region - 01/09/2024
A planned outage of Armidale - Sapphire 8E 330kv Line in the NSW region was scheduled from 1630 hrs 31/08/2024 to 0910 hrs 02/09/2024.
The outage has been rescheduled for 1630 hrs 31/08/2024 to 1800 hrs 02/09/2024.
The following constraint set(s) invoked at 1630 hrs 31/08/2024
N-ARSR_8E
N-TW_SVC
N-DM_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 kV line - NSW region - 31/08/2024
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 kV line - NSW region - 31/08/2024
At 1630 hrs 31/08/2024 there was a short notice outage of Armidale - Sapphire 8E 330 kV line.
The following constraint set(s) invoked at 1630 hrs 31/08/2024
N-ARSR_8E, N-TW_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
QNI Minor testing (NSW to Qld) 28th August 2024
Refer to market notice 117650
There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 850 MW on Wednesday 28th August 2024 from 1300 to 1700hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
Inter-regional transfer limit variation - Dumaresq 330 kV SVC - NSW region - 28/08/2024
Inter-regional transfer limit variation - Dumaresq 330 kV SVC - NSW region - 28/08/2024
At 1125 hrs 28/08/2024 there was a short notice outage of Dumaresq 330 kV SVC.
The following constraint set(s) invoked at 1125 hrs 28/08/2024
N-DM_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 28/08/2024
In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_SYDS_55E0E615 from 0900 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
Network Augmentation Commissioned - VIC Region - 27/08/2024
Network Augmentation Commissioned - VIC Region - 27/08/2024
Cressy - Golden Plains No. 1 220 kV Line has been commissioned.
Golden Plains Terminal Station has been commissioned.
Manager NEM Real Time Operations