Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 28/08/2024
In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_SYDS_55E0E615 from 0900 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
CHG0095127 | Completed | Pre-Production | Pre-Prod NEM Reform - RMI (Retail Market Improvements) MSATS and eMDM Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod NEM Reform - RMI (Retail Market Improvements) MSATS and eMDM Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0096175 | Production | EMMS Production Bay transfer
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: EMMS Production Bay transfer
Change Start Date & Time: 02/09/2024 09:00:00 AEST
Change End Date & Time: 04/09/2024 16:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: EMMS Bay transfer is scheduled for 3rd September is not expected to have any impact. If any issues are identified because of this maintenance activity, please contact the AEMO Support Hub 1300 236 600.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.
Cancellation - Inter-Regional Transfer limit variation - Murraylink 27/08/2024
Cancellation - Inter-Regional Transfer limit variation - Murraylink 27/08/2024
Refer AEMO Electricity Market Notice 117831
To manage power system security in the Victoria region, AEMO invoked the following network constraint.
Constraint Set invoked from 10:40 hrs 27/08/2024 to 11:00 hrs 27/08/2024
I:SVML_120
This constraint set contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Murraylink 27/08/2024
Inter-Regional Transfer limit variation - Murraylink 27/08/2024
To manage power system security in the Victoria region, AEMO has invoked the following network constraint.
Constraint Set invoked at 10:40 HRS 27/08/2024
I:SVML_120
This constraint set contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Manager NEM Real Time Operations
CHG0095221 | Cancelled | Production | A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Gas Hub
Change Title: A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
CHG0091459 | Cancelled | Production | MSATS CATS & URM Site Transfer BNE to NOR Data Centre
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS CATS & URM Site Transfer BNE to NOR Data Centre
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
Inter-regional transfer limit variation - Cherry Gardens - Torrens Island B 275kV Line - SA region - 26/08/2024
Inter-regional transfer limit variation - Cherry Gardens - Torrens Island B 275kV Line - SA region - 26/08/2024
At 0250 hrs 26/08/2024 there was a short notice outage of Cherry Gardens - Torrens Island B 275kV Line.
The following constraint set(s) invoked at 0250 hrs 26/08/2024
S-CGTI
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation -Redcliffs No 2 220 kV Bus - VIC region - 25/08/2024
Inter-regional transfer limit variation -Redcliffs No 2 220 kV Bus - VIC region - 25/08/2024
A planned outage of Redcliffs No 2 220 kV Bus in the VIC region was scheduled from 0630 hrs 25/08/2024 to 1730 hrs 25/08/2024.
The outage has been cancelled at 0805 hrs.
The following constraint set(s) were invoked
Constraint Sets: V-KMRC, V-RCTS220CAPAUTO
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,T-V-MNSP1,V-SA,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations