[EventId:202411180945_review] Prices for interval 18-Nov-2024 09:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 0940 hrs on 18 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 18-Nov-2024 09:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411180940_review] Prices for interval 18-Nov-2024 09:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 0935 hrs on 18 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 18-Nov-2024 09:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411180935_review] Prices for interval 18-Nov-2024 09:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 0930 hrs on 18 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 18-Nov-2024 09:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411180930_review] Prices for interval 18-Nov-2024 09:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 0925 hrs on 18 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 18-Nov-2024 09:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411180925_review] Prices for interval 18-Nov-2024 09:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 0920 hrs on 18 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 18-Nov-2024 09:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer AEMO Electricity Participant Notice 120577
The MINTARO MINTARO GAS direction is now expected to stay in place until 1900 hrs 18/11/2024.
The direction update is issued at 0830 hrs 18/11/2024.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 18/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120575 is cancelled at 1945 hrs 17/11/2024.
Manager NEM Real Time Operations
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer AEMO Electricity Participant Notice 120554
The MINTARO MINTARO GAS direction is now expected to stay in place until 2130 hrs 18/11/2024.
The direction update is issued at 1915 hrs 17/11/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 18/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1830 hrs 18/11/2024 to 1900 hrs 18/11/2024.
The forecast capacity reserve requirement is 1061 MW.
The minimum capacity reserve available is 1045 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations