Filter by category
Filter by Date
CHG0098106 | Production | EMMS Production Bay transfer
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: EMMS Production Bay transfer
Change Start Date & Time: 05/09/2024 08:00:00 AEST
Change End Date & Time: 06/09/2024 17:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: EMMS Bay transfer is scheduled for 5th September is not expected to have any impact. If any issues are identified because of this maintenance activity, please contact the AEMO Support Hub 1300 236 600.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .
Fast Frequency Response Market - Removal of L1 FCAS dispatch cap from 9th September 2024
Following review of the operation of the Very Fast FCAS market, from 1300 hrs AEST on Monday 9th September AEMO will remove the 225 MW cap on dispatch of Very Fast Lower (L1) Contingency FCAS.
The 225 MW cap on dispatch of L1 FCAS sits well above typical disaptch volumes, and no immediate impact is expected from this change.
No other changes to the dispatch of Very Fast FCAS or FCAS constraint equation changes will be made on this date.
For information on the Fast Frequency Response (FFR) initiative please visit the website at: https://www.aemo.com.au/initiatives/major-programs/fast-frequency-response
Andrew Groom
AEMO Operations
CHG0097011 | Production | AEMO will be undertaking maintenance activities on the EMMS - MATRIXIDR,Stpasa system
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the EMMS - MATRIXIDR,Stpasa system
Change Start Date & Time: 05/09/2024 20:00:00 AEST
Change End Date & Time: 06/09/2024 02:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: AEMO will be undertaking maintenance activities on the EMMS - MATRIXIDR,Stpasa system. Whilst no outage is expected there is potential for transient performance degradation during the change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0097010 | Production | AEMO will be undertaking maintenance activities on the RCM system
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the RCM system
Change Start Date & Time: 05/09/2024 20:00:00 AEST
Change End Date & Time: 06/09/2024 02:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: AEMO will be undertaking maintenance activities on the PrudentialService, RCM, Forecast system. Whilst no outage is expected there is potential for transient performance degradation during the change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0096973 | Production | AEMO will be undertaking maintenance activities on the RCM system
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the RCM system
Change Start Date & Time: 04/09/2024 20:00:00 AEST
Change End Date & Time: 04/09/2024 23:59:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: AEMO will be undertaking maintenance activities on the RCM system. Whilst no outage is expected there is potential for transient performance degradation during the change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0091339 | Completed | Production | NSW Marketnet Router Replacement
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Market Network
Change Title: NSW Marketnet Router Replacement
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Network Augmentation Commissioned - NSW Region - 01/09/2024
Network Augmentation Commissioned - NSW Region - 01/09/2024
At 2125 hrs. Buronga -Redcliffs X9 220 kV line has been commissioned.
At 2125 hrs. Buronga -Redcliffs OX1 220 kV line has been de-commissioned.
Manager NEM Real Time Operations
CHG0089859 | Completed | Pre-Production | Maintenance activities to be performed on the Gas Short Term Trading Market Systems Pre-Production.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Gas FRC - CATS
Change Title: Maintenance activities to be performed on the Gas Short Term Trading Market Systems Pre-Production.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
QNI Minor testing (NSW to Qld) 28th August 2024
Refer to market notice 117650
There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 850 MW on Wednesday 28th August 2024 from 1300 to 1700hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations