118998INTER-REGIONAL TRANSFER17/10/2024 07:20:04 PM

Inter-regional transfer limit variation - Brinkworth- Red Hill- Bungama 132kV lines - SA region - 17/10/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Brinkworth- Red Hill- Bungama 132kV lines - SA region - 17/10/2024

At 1846 hrs 17/10/2024 there was an unplanned outage of Brinkworth- Red Hill- Bungama 132kV lines.

The following constraint set(s) invoked at 1855 hrs 17/10/2024
S-BRBG

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
118997INTER-REGIONAL TRANSFER17/10/2024 07:18:47 PM

Inter-regional transfer limit variation - Hummocks - Bungama 132kV line - SA region - 17/10/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hummocks - Bungama 132kV line - SA region - 17/10/2024

At 1842 hrs 17/10/2024 there was an unplanned outage of Hummocks - Bungama 132kV line.

The following constraint set(s) invoked at 1850 hrs 17/10/2024
S-HUBG

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
118996INTER-REGIONAL TRANSFER17/10/2024 07:13:32 PM

Inter-regional transfer limit variation - Blyth West - Munno Para 275kV line- SA region - 17/10/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Blyth West - Munno Para 275kV line - SA region - 17/10/2024

At 1848 hrs 17/10/2024 there was an unplanned outage of Blyth West - Munno Para 275kV line.

The following constraint set(s) invoked at 1855 hrs 17/10/2024
S-BWMP

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
118934MARKET SYSTEMS16/10/2024 03:56:26 PM

CHG0098812 | Completed | Pre-Production | Pre-Prod MSATS and eMDM November Maintenance Release

Change Number: CHG0098812

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: MSATS - Market Settlement & Transfer System

Change Title: Pre-Prod MSATS and eMDM November Maintenance Release

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
118911MARKET SYSTEMS15/10/2024 01:53:48 PM

CHG0098814 | Production | MSATS and eMDM November Maintenance Release

Change Number: CHG0098814

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)

Change Title: MSATS and eMDM November Maintenance Release

Change Start Date & Time: 27/10/2024 10:00:00 AEST
Change End Date & Time: 27/10/2024 17:00:00 AEST
Outage Start Date & Time: 27/10/2024 10:00:00 AEST
Outage End Date & Time: 27/10/2024 14:00:00 AEST

Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.
     
118851MINIMUM SYSTEM LOAD13/10/2024 01:01:01 PM

Cancellation - MSL1- VIC Region at 1300 hrs 13/10/2024.

AEMO ELECTRICITY MARKET NOTICE

Cancellation - MSL1- VIC Region at 1300 hrs 13/10/2024.

Refer to Market Notice 11836 for MSL1.

Manager NEM Real Time Operations
     
118836MINIMUM SYSTEM LOAD13/10/2024 09:11:36 AM

Minimum System Load 1 (MSL1) in the VIC Region on 13/10/2024

AEMO ELECTRICITY MARKET NOTICE

Minimum System Load 1 (MSL1) in the VIC Region on 13/10/2024

Update to Market Notice 118834 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1030 hrs 13/10/2024 to 1330 hrs 13/10/2024.

Minimum regional demand is forecast to be 1265 MW at 1230 hrs, and the advisory threshold is:
- MSL1 - 1560 MW
- MSL2 - 1060 MW
- MSL3 - 560 MW

MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold. Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem

AEMO is seeking a market response such as rescheduling of planned network outages and increasing electricity consumption.
An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in actions such as recalling network outages, the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.

Manager NEM Real Time Operations
     
118832MINIMUM SYSTEM LOAD13/10/2024 05:10:06 AM

Cancellation - MSL1- VIC Region at 0500 hrs 13/10/2024.

AEMO ELECTRICITY MARKET NOTICE

Cancellation - MSL1- VIC Region at 0500 hrs 13/10/2024.

Refer to Market Notice 118809 for MSL1.

Manager NEM Real Time Operations
     
118817MINIMUM SYSTEM LOAD12/10/2024 12:53:52 PM

Cancellation - MSL1- VIC Region at 1247 hrs 12/10/2024.

AEMO ELECTRICITY MARKET NOTICE

Cancellation - MSL1- VIC Region at 1247 hrs 12/10/2024.

Refer to Market Notice 118803 for MSL1.

Manager NEM Real Time Operations
     