120420MARKET INTERVENTION14/11/2024 04:52:42 PM

Cancellation - AEMO Intervention Event - VIC region 14/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - VIC region 14/11/2024

Refer to Market Notice 120404

The AEMO Intervention Event and all associated directions are cancelled from 1700 hrs on 14/11/2024.


Manager NEM Real Time Operations
     
120419MARKET INTERVENTION14/11/2024 06:23:21 PM

Cancellation: Direction issued to: Snowy Hydro Limited - MURR2-3 MURRAY2

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Snowy Hydro Limited - MURR2-3 MURRAY2

Refer to Market Notice 120435

Direction is cancelled from: 1820 hrs 14/11/2024

Manager NEM Real Time Operations
     
120418MARKET INTERVENTION14/11/2024 06:24:29 PM

Cancellation: Direction issued to: Snowy Hydro Limited - MURR2-2 MURRAY2

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Snowy Hydro Limited - MURR2-2 MURRAY2

Refer to Market Notice 120449

Direction is cancelled from: 1820 hrs 14/11/2024

Manager NEM Real Time Operations
     
120417MARKET INTERVENTION15/11/2024 08:03:12 AM

Cancellation: Direction issued to: EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO

Refer to Market Notice 120475

Direction is cancelled from: 0800 hrs 15/11/2024

Manager NEM Real Time Operations
     
120416MARKET INTERVENTION15/11/2024 08:02:02 AM

Cancellation: Direction issued to: EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO

Refer to Market Notice 120474

Direction is cancelled from: 0800 hrs 15/11/2024

Manager NEM Real Time Operations
     
120415MARKET INTERVENTION14/11/2024 12:42:44 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 15/11/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
120414NON-CONFORMANCE14/11/2024 12:00:20 PM

NON-CONFORMANCE Region QLD1 Thursday, 14 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 14 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 14/11/2024 08:40 to 14/11/2024 12:00
Amount: 30 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
120412MARKET INTERVENTION14/11/2024 09:53:55 AM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 120381

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1800 hrs 14/11/2024.

The direction update is issued at 0950 hrs 14/11/2024.

Manager NEM Real Time Operations
     
120411NON-CONFORMANCE14/11/2024 08:10:16 AM

NON-CONFORMANCE Region QLD1 Thursday, 14 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 14 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 14/11/2024 08:05 to 14/11/2024 08:10
Amount: -47 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     