Market Notices

119573MARKET INTERVENTION28/10/2024 03:13:31 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 119414


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1500 hrs 28/10/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 1510 hrs 28/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1700 hrs 29/10/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
119563MARKET INTERVENTION28/10/2024 12:11:07 PM

Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer AEMO Electricity Participant Notice 119494

The MINTARO MINTARO GAS direction is now expected to stay in place until 1600 hrs 28/10/2024.

The direction update is issued at 1210 hrs 27/10/2024.

Manager NEM Real Time Operations
     
119499MARKET SYSTEMS27/10/2024 03:30:17 PM

CHG0098814 | Completed | Production | MSATS and eMDM November Maintenance Release

Change Number: CHG0098814
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS and eMDM November Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
119498MARKET INTERVENTION27/10/2024 03:03:02 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119444

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 29/10/2024.

The direction update is issued at 1500 hrs 27/10/2024.

Manager NEM Real Time Operations
     
119497MARKET INTERVENTION27/10/2024 02:39:46 PM

Minimum System Load 1 (MSL1) in the VIC Region on 03/11/2024

AEMO ELECTRICITY MARKET NOTICE
Minimum System Load 1 (MSL1) in the VIC Region on 03/11/2024

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1200 hrs 03/11/2024 to 1300 hrs 03/11/2024.

Minimum regional demand is forecast to be 1755 MW at 1230 hrs, and the advisory threshold is:
MSL1 - 1795 MW
MSL2 - 1295 MW
MSL3 - 795 MW

MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold. Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem
AEMO is seeking a market response such as rescheduling of planned network outages and increasing electricity consumption.

An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in actions such as recalling network outages, the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.

Manager NEM Real Time Operations
     
119494MARKET INTERVENTION27/10/2024 01:02:20 PM

Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer AEMO Electricity Participant Notice 119467

The MINTARO MINTARO GAS direction is now expected to stay in place until 1700 hrs 28/10/2024.

The direction update is issued at 1300 hrs 27/10/2024.

Manager NEM Real Time Operations
     
119468MARKET INTERVENTION27/10/2024 09:16:29 AM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 119466

Direction is cancelled from: 0915 hrs 27/10/2024

Manager NEM Real Time Operations
     
119467MARKET INTERVENTION27/10/2024 08:41:55 AM

Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer AEMO Electricity Participant Notice 119464

The MINTARO MINTARO GAS is now expected to synchronise at 0915 hrs 27/10/2024.

The MINTARO MINTARO GAS direction is now expected to stay in place until 1415 hrs 27/10/2024.

The direction update is issued at 0835 hrs 27/10/2024.

Manager NEM Real Time Operations
     
119466MARKET INTERVENTION27/10/2024 08:40:52 AM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer AEMO Electricity Participant Notice 119463

The PPCCGT PELICAN POINT direction is now expected to stay in place until 0915 hrs 27/10/2024.

The direction update is issued at 0830 hrs 27/10/2024.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm