116730RESERVE NOTICE20/05/2024 05:17:20 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 20/05/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 20/05/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 1630 MW
The minimum capacity reserve available is 1028 MW

Manager NEM Real Time Operations
116689RESERVE NOTICE18/05/2024 06:42:10 PM

Cancellation of Actual (LOR1) condition in the NSW region - 18/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 18/05/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No. 116688 is cancelled at 1840 hrs 18/05/2024.

Manager NEM Real Time Operations
116688RESERVE NOTICE18/05/2024 05:58:11 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 18/05/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 18/05/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs

The capacity reserve requirement is 1430 MW
The minimum capacity reserve available is 1314 MW

Manager NEM Real Time Operations
116630GENERAL NOTICE15/05/2024 06:00:51 PM

Update - Network Augmentation Commissioned - QLD Region - 15/05/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Network Augmentation Commissioned - QLD Region - 15/04/2024

Refer Market notice: 115974 and 116446

Guybal Munjan 275 kV Switching Station has been commissioned.

The former Ross - Chalumbin No. 857 and Ross - Chalumbin No. 858 275 kV lines have been replaced with the following lines:

H13 Ross - H93 Guybal Munjan No. 8916 275 kV line
H13 Ross - H93 Guybal Munjan No. 8917 275 kV line

H93 Guybal Munjan - H32 Chalumbin No. 857 275 kV line
H93 Guybal Munjan - H32 Chalumbin No. 858 275 kV line


Manager NEM Real Time Operations
116617ADMINISTERED PRICE CAP15/05/2024 03:55:00 AM

[EventId:203] AP ENDED for ENERGY in NSW1 at 15 May 2024 03:55

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0355 hrs on 14 May 2024

ADMINISTERED PRICE PERIOD ENDS in NSW1 region.

In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO is notifying market participants that the administered price period declared for the NSW1 region in market notice 116607 will end at 0400 hrs on 15 May 2024.


This is an AEMO autogenerated Market Notice.
116616RESERVE NOTICE14/05/2024 06:24:48 PM

Cancellation of Actual (LOR1) condition in the Qld Region - 14/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the Qld region - 14/05/2024

The Actual LOR1 Condition in the Qld Region advised in AEMO Electricity Market Notice No.116615 is cancelled at 1815 hrs 14/05/2024.

Manager NEM Real Time Operations
116615RESERVE NOTICE14/05/2024 05:43:15 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/05/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 14/05/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.

The Actual LOR1 condition is forecast to exist until 1800 hrs.

The forecast capacity reserve requirement is 830 MW.
The minimum capacity reserve available is 727 MW.


Manager NEM Real Time Operations
116607ADMINISTERED PRICE CAP14/05/2024 03:55:10 AM

[EventId:203] AP STARTED for ENERGY in NSW1 at 14 May 2024 03:55

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0355 hrs on 14 May 2024

ADMINISTERED PRICE PERIOD DECLARED in NSW1 region.

AEMO has determined that the rolling sum of the uncapped spot prices for the NSW1 region over the previous 2016 trading intervals has exceeded the cumulative price threshold (CPT) of $1,490,200.00.

In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO has determined that an administered price period will commence at the trading interval starting 0405 hrs on 14 May 2024 and will continue through to the end of that trading day.

An administered price cap (APC) of 600 $/MWh will apply to all trading intervals during this administered price period. This APC will apply to spot prices and to all market ancillary service prices in the NSW1 region.

An administered floor price (AFP) of -600 $/MWh will apply to spot prices.

AEMO will continue to monitor the rolling sum of the uncapped spot prices and issue further Market Notices as required.

This is an AEMO autogenerated Market Notice.
116606ADMINISTERED PRICE CAP14/05/2024 03:55:01 AM

[EventId:202] AP ENDED for ENERGY in NSW1 at 14 May 2024 03:55

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0355 hrs on 13 May 2024

ADMINISTERED PRICE PERIOD ENDS in NSW1 region.

In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO is notifying market participants that the administered price period declared for the NSW1 region in market notice 116604 will end at 0400 hrs on 14 May 2024.


This is an AEMO autogenerated Market Notice.