[EventId:202411060805_NRM_SA1_VIC1_started] NEGRES CONSTRAINT NRM_SA1_VIC1 started operating from 06 November 2024 08:05
Issued by Australian Energy Market Operator Ltd at 0805 hrs on 6 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 6 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the SA to VIC directional interconnector.
The negative residue constraint set NRM_SA1_VIC1 commenced operating from 0805 hrs on 6 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 06/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1800 hrs 06/11/2024 to 1830 hrs 06/11/2024.
The forecast capacity reserve requirement is 1108 MW.
The minimum capacity reserve available is 1086 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119927 has been updated at 0430 hrs to the following:
[1.] From 1800 hrs 06/11/2024 to 1830 hrs 06/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1312 MW.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119931
The TORRB4 TORRENS ISLAN unit is now expected to synchronise at 0230 hrs 06/11/2024 direction is now expected to stay in place until 1700 hrs 06/11/2024.
The direction update is issued at 0105 hrs 06/11/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119929
The TORRB4 TORRENS ISLAN unit is now expected to synchronise at 0200 hrs 06/11/2024 direction is now expected to stay in place until 1700 hrs 06/11/2024.
The direction update is issued at 2155 hrs 05/11/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119924
The TORRB4 TORRENS ISLAN unit is now expected to synchronise at 2330 hrs 05/11/2024 direction is now expected to stay in place until 1700 hrs 06/11/2024.
The direction update is issued at 1855 hrs 05/11/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119911 has been updated at 1700 hrs to the following:
[1.] From 1800 hrs 06/11/2024 to 1830 hrs 06/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1278 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region [beginning] on 05/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119913 is cancelled at 1650 hrs 05/11/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119875
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 06/11/2024.
The direction update is issued at 1610 hrs 05/11/2024.
Manager NEM Real Time Operations